8779 N RINCON AVE 91352

Certificate Information: 8779 N RINCON AVE 91352

Application / Permit
24014-20000-00968
Plan Check / Job No.
B24VN03212
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: INTERIOR REMODEL AND 29'-1" X 13'-5" ADDITION TO (E) SFD. ALL WORK PER WFPP.
Permit Issued
Issued on 7/25/2024
Issuing Office
Current Status
CofO Issued on 4/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/12/2024 APPLICANT
Assigned to Plan Check Engineer 3/15/2024 LUISANGEL VALENZUELA
Corrections Issued 3/16/2024 LUISANGEL VALENZUELA
Applicant returned to address corrections 5/3/2024 LUISANGEL VALENZUELA
Plan Check Approved 7/12/2024 PINANK PATEL
Issued 7/25/2024 APPLICANT
CofO in Progress 4/2/2025 MATTHEW NELSON
Permit Finaled 4/10/2025 RUBEN SALAS
CofO Issued 4/10/2025 RUBEN SALAS
Permit Finaled 4/10/2025 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/12/2024 BIAINA HARITUNIAN
Sewer availability Cleared 4/12/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 4/17/2024 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/22/2024 Conditional Approval MATTHEW NELSON
Excavation/Setback/Form/Re-Bar 8/22/2024 Corrections Issued MATTHEW NELSON
Footing/Foundation/Slab 8/22/2024 Corrections Issued MATTHEW NELSON
Excavation/Setback/Form/Re-Bar 8/23/2024 Approved MATTHEW NELSON
Footing/Foundation/Slab 8/23/2024 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 8/28/2024 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Rough 8/28/2024 Partial Approval MATTHEW NELSON
Underground Mechanical 8/28/2024 Not Ready for Inspection MATTHEW NELSON
Wood Frame 8/28/2024 Partial Approval MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 9/5/2024 Approved MATTHEW NELSON
BUILDING-Rough-Frame 9/24/2024 Partial Approval MATTHEW NELSON
ELECTRICAL-Rough 9/24/2024 Approved MATTHEW NELSON
Green Building Rough 9/24/2024 Approved MATTHEW NELSON
MERV13>=Rough 9/24/2024 Approved MATTHEW NELSON
PLUMBING-Rough 9/24/2024 Approved MATTHEW NELSON
BUILDING-Rough-Frame 9/26/2024 Not Ready for Inspection MATTHEW NELSON
Interior/Exterior Lathing 9/26/2024 Approved MATTHEW NELSON
BUILDING-Rough-Frame 10/1/2024 Approved MATTHEW NELSON
HVAC-Rough 10/1/2024 Approved MATTHEW NELSON
Insulation 10/1/2024 Approved MATTHEW NELSON
Drywall Nailing 10/7/2024 No Access for Inspection MATTHEW NELSON
Interior/Exterior Lathing 10/7/2024 No Access for Inspection MATTHEW NELSON
Shower Pan 10/7/2024 No Access for Inspection MATTHEW NELSON
Drywall Nailing 10/9/2024 Approved MATTHEW NELSON
ELECTRICAL-Rough 10/9/2024 Approved MATTHEW NELSON
Insulation 10/9/2024 Approved MATTHEW NELSON
Interior/Exterior Lathing 10/9/2024 Corrections Issued MATTHEW NELSON
Interior/Exterior Lathing 10/18/2024 Approved DAVID ANDERSON
Shower Pan 10/18/2024 Approved DAVID ANDERSON
Final 2/11/2025 Not Ready for Inspection MATTHEW NELSON
Green Building Final 2/11/2025 Not Ready for Inspection MATTHEW NELSON
MERV13>=Final 2/11/2025 Not Ready for Inspection MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 2/11/2025 SGSOV Not Ready MATTHEW NELSON
Smoke Detectors 2/11/2025 Not Ready for Inspection MATTHEW NELSON
Final 3/21/2025 Corrections Issued MATTHEW NELSON
Green Building Final 3/21/2025 Corrections Issued MATTHEW NELSON
MERV13>=Final 3/21/2025 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 3/21/2025 SGSOV Approved MATTHEW NELSON
Smoke Detectors 3/21/2025 Approved MATTHEW NELSON
Final 3/28/2025 Corrections Issued MATTHEW NELSON
Green Building Final 3/28/2025 Approved MATTHEW NELSON
Final 4/1/2025 OK to Issue CofO MATTHEW NELSON