8237-8239 N JELLICO AVE 91325
Certificate Information: 8237-8239 N JELLICO AVE 91325
- Application / Permit
- 24014-20000-00917
- Plan Check / Job No.
- B24VN03032
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE ATTACHED CARPORT AND ADD A 31'6"X12'0" 1ST & 2ND FLOOR ADDITION FOR SFD & A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 4/24/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/7/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/21/2024 | MARVEL DELACRUZ |
| Corrections Issued | 3/28/2024 | MARVEL DELACRUZ |
| Quality Review Completed | 3/29/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 4/3/2024 | APPLICANT |
| Plan Check Approved | 4/24/2024 | MARVEL DELACRUZ |
| Issued | 4/24/2024 | APPLICANT |
| CofO in Progress | 3/19/2025 | SALVADOR MARTINEZ |
| Permit Finaled | 7/10/2025 | RUBEN SALAS |
| CofO Issued | 7/10/2025 | RUBEN SALAS |
| Permit Finaled | 7/10/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/9/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 4/9/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 4/10/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 4/10/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Morales,, Carlos Alberto; Lic. No.: C69972 | 38100 SAN MATEO AVE PALMDALE, CA 93551 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/15/2024 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 5/15/2024 | Corrections Issued | RAUL OLAGI |
| Special/Order Compliance | 5/15/2024 | Corrections Issued | JUAN VALENZUELA |
| Footing/Foundation/Slab | 5/21/2024 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 5/21/2024 | Partial Approval | RAUL OLAGI |
| Wood Frame | 6/4/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2024 | Partial Approval | RAUL OLAGI |
| Sewer | 6/5/2024 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2024 | Partial Approval | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 8/9/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2024 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 8/9/2024 | Corrections Issued | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 8/16/2024 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 8/16/2024 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 8/16/2024 | Approved | RAUL OLAGI |
| HVAC-Rough | 8/16/2024 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 8/16/2024 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 8/19/2024 | Not Ready for Inspection | RAUL OLAGI |
| HVAC-Rough | 8/19/2024 | Not Ready for Inspection | RAUL OLAGI |
| BUILDING-Rough-Frame | 8/26/2024 | Corrections Issued | RAUL OLAGI |
| HVAC-Rough | 8/26/2024 | Partial Approval | RAUL OLAGI |
| Shower Pan | 8/26/2024 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 9/11/2024 | Approved | RAUL OLAGI |
| Insulation | 9/11/2024 | Corrections Issued | RAUL OLAGI |
| Interior/Exterior Lathing | 9/11/2024 | Partial Approval | RAUL OLAGI |
| Drywall Nailing | 10/23/2024 | Approved | GAREN HAYRAPETYAN |
| Green Building Rough | 10/23/2024 | Approved | GAREN HAYRAPETYAN |
| Deputy Drilled-In Anchors | 11/1/2024 | Conditional Approval | RAUL OLAGI |
| Gas Test | 12/4/2024 | Partial Inspection | SALVADOR MARTINEZ |
| Underground Mechanical | 12/4/2024 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 12/10/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Service/Power Release | 12/10/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Underground Mechanical | 12/10/2024 | Approved | SALVADOR MARTINEZ |
| Final | 1/16/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Final | 1/16/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 1/16/2025 | SGSOV Not Ready | SALVADOR MARTINEZ |
| Smoke Detectors | 1/16/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 2/7/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Final | 2/7/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Final | 2/7/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| HVAC-Final | 2/7/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Final | 2/7/2025 | Corrections Issued | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 2/7/2025 | SGSOV Approved | SALVADOR MARTINEZ |
| Service/Power Release | 2/7/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Smoke Detectors | 2/7/2025 | Approved | SALVADOR MARTINEZ |
| Final | 2/19/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Final | 2/19/2025 | Approved | SALVADOR MARTINEZ |
| Final | 2/24/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Final | 3/18/2025 | OK to Issue CofO | SALVADOR MARTINEZ |
| Service/Power Release | 3/18/2025 | Approved | SALVADOR MARTINEZ |