9502-9504 N LANGDON AVE 91343
Certificate Information: 9502-9504 N LANGDON AVE 91343
- Application / Permit
- 24014-20000-00911
- Plan Check / Job No.
- B24VN03023
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- ADD TO (5' x 20') & CONVERT (E) 2-CAR GARAGE TO DWELLING UNIT per SB9 Two-Unit Development Ca Govt Code 65852.21; ALL WORK PER WFPP
- Permit Issued
- Issued on 6/12/2024
- Issuing Office
- Current Status
- CofO Issued on 7/22/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/6/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/21/2024 | SEAN SHAHMIRI |
| Corrections Issued | 3/28/2024 | SEAN SHAHMIRI |
| Quality Review Completed | 3/28/2024 | STEVEN KIM |
| Building Plans Picked Up | 4/9/2024 | APPLICANT |
| Plan Check Approved | 6/12/2024 | RAPHAEL ROSAS |
| Issued | 6/12/2024 | APPLICANT |
| CofO in Progress | 6/26/2025 | VINCENT HANLEY |
| Permit Finaled | 7/22/2025 | RUBEN SALAS |
| CofO Issued | 7/22/2025 | RUBEN SALAS |
| Permit Finaled | 7/22/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/4/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 4/4/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 5/6/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 5/6/2024 | BIAINA HARITUNIAN |
| Hydrant and Access approval | Cleared | 5/9/2024 | JOHN CONNEALLY |
| Senate Bill 9 | Cleared | 5/16/2024 | ALEX VELA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/23/2024 | Conditional Approval | ROBERT GOLD |
| Excavation/Setback/Form/Re-Bar | 7/30/2024 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 7/30/2024 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 7/30/2024 | Partial Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 8/15/2024 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/15/2024 | Approved | VINCENT HANLEY |
| MERV13>=Rough | 8/15/2024 | Not Ready for Inspection | VINCENT HANLEY |
| ELECTRICAL-Rough | 9/25/2024 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Rough | 9/25/2024 | Approved | VINCENT HANLEY |
| Sewer | 9/25/2024 | Approved | VINCENT HANLEY |
| Underground Mechanical | 9/25/2024 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 9/27/2024 | Approved | VINCENT HANLEY |
| HVAC-Rough | 9/27/2024 | Approved | VINCENT HANLEY |
| Insulation | 9/30/2024 | Partial Approval | VINCENT HANLEY |
| Drywall Nailing | 10/1/2024 | Not Ready for Inspection | VINCENT HANLEY |
| Green Building Rough | 10/1/2024 | Not Ready for Inspection | VINCENT HANLEY |
| Green Building Final | 10/4/2024 | Approved | VINCENT HANLEY |
| Green Building Rough | 10/4/2024 | Approved | VINCENT HANLEY |
| Insulation | 10/4/2024 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 10/4/2024 | Partial Approval | VINCENT HANLEY |
| MERV13>=Rough | 10/4/2024 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 10/10/2024 | Approved | VINCENT HANLEY |
| Drywall Nailing | 10/10/2024 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 10/10/2024 | Approved | VINCENT HANLEY |
| Shower Pan | 10/10/2024 | Approved | VINCENT HANLEY |
| Service/Power Release | 10/31/2024 | Corrections Issued | VINCENT HANLEY |
| ELECTRICAL-Final | 11/1/2024 | Corrections Issued | VINCENT HANLEY |
| Service/Power Release | 11/13/2024 | Not Ready for Inspection | VINCENT HANLEY |
| ELECTRICAL-Final | 3/24/2025 | Corrections Issued | VINCENT HANLEY |
| Final | 3/24/2025 | Corrections Issued | VINCENT HANLEY |
| MERV13>=Final | 3/24/2025 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 3/24/2025 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 3/24/2025 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 4/23/2025 | Approved | VINCENT HANLEY |
| Final | 4/23/2025 | Corrections Issued | VINCENT HANLEY |
| HVAC-Final | 4/23/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 4/23/2025 | Approved | VINCENT HANLEY |
| Service/Power Release | 4/24/2025 | Approved | VINCENT HANLEY |
| Final | 6/26/2025 | OK to Issue CofO | VINCENT HANLEY |