11825 W ART ST 91352

Certificate Information: 11825 W ART ST 91352

Application / Permit
24014-20000-00906
Plan Check / Job No.
B24VN02997
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL AND ADDITION TO AN EXISTING 1-STORY S.F.D. ADDITION OF PORCH. WORK PER WFPP. FIRE SPRINKLER REQUIRED NFPA-13D
Permit Issued
Issued on 8/6/2024
Issuing Office
Current Status
CofO Issued on 10/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/19/2024 APPLICANT
Assigned to Plan Check Engineer 3/22/2024 SERGIO MUNIZ
Corrections Issued 3/23/2024 SERGIO MUNIZ
Applicant returned to address corrections 5/8/2024 SERGIO MUNIZ
Plan Check Approved 5/23/2024 SERGIO MUNIZ
Issued 8/6/2024 APPLICANT
CofO in Progress 9/15/2025 MATTHEW NELSON
CofO Issued 10/14/2025 RUBEN SALAS
Permit Finaled 10/14/2025 RUBEN SALAS

Permit Application Clearance Information

Clean Up Green Up Cleared 4/2/2024 BRENNEN OBETO
Tract Map conditions Cleared 4/2/2024 BRENNEN OBETO
Eng Process Fee Ord 176,300 Cleared 4/30/2024 BIAINA HARITUNIAN
Sewer availability Cleared 4/30/2024 BIAINA HARITUNIAN
Low Impact Development (LID) Cleared 5/1/2024 ERNEST TSE
Roof/Waste drainage to street Cleared 5/7/2024 BIAINA HARITUNIAN

Contact Information

Contractor Markarian Setrag; Lic. No.: 832632-B       ,
Contractor Pampa Investment Inc; Lic. No.: 832632-B       ,
Engineer Moser,, Bradley Charles; Lic. No.: NA68803       ,

Inspector Information

WILLIAM WREN, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/8/2024 Approved MATTHEW NELSON
Footing/Foundation/Slab 8/8/2024 Approved MATTHEW NELSON
Footing/Foundation/Slab 9/17/2024 Approved MATTHEW NELSON
Underground Mechanical 9/17/2024 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Rough 9/24/2024 Partial Approval MATTHEW NELSON
Wood Frame 9/24/2024 Partial Approval MATTHEW NELSON
Wood Frame 10/4/2024 Partial Approval MATTHEW NELSON
BUILDING-Rough-Frame 11/20/2024 Not Ready for Inspection MATTHEW NELSON
ELECTRICAL-Rough 11/20/2024 Approved MATTHEW NELSON
Green Building Rough 11/20/2024 Approved MATTHEW NELSON
HVAC-Rough 11/20/2024 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Rough 11/20/2024 Corrections Issued MATTHEW NELSON
BUILDING-Rough-Frame 12/2/2024 Approved MATTHEW NELSON
Interior/Exterior Lathing 12/2/2024 Approved MATTHEW NELSON
Insulation 12/18/2024 Approved MATTHEW NELSON
Drywall Nailing 1/21/2025 Approved MATTHEW NELSON
Interior/Exterior Lathing 1/29/2025 Approved MATTHEW NELSON
Final 5/14/2025 Corrections Issued NICHOLAS TROWBRIDGE
Green Building Final 5/14/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
SGSOV-Seismic Gas S/O Valve 5/14/2025 SGSOV Approved NICHOLAS TROWBRIDGE
Smoke Detectors 5/14/2025 Approved NICHOLAS TROWBRIDGE
Final 6/13/2025 Partial Inspection MATTHEW NELSON
Final 6/27/2025 Corrections Issued MATTHEW NELSON
Green Building Final 6/27/2025 Corrections Issued MATTHEW NELSON
Final 9/15/2025 OK to Issue CofO MATTHEW NELSON
Green Building Final 9/15/2025 Approved MATTHEW NELSON