10024 N GENESTA AVE 91325
Certificate Information: 10024 N GENESTA AVE 91325
- Application / Permit
- 24014-20000-00900
- Plan Check / Job No.
- B24VN02965
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan. Addition and remodel (E) SFD and attached garage. Increase ceiling height. Per engineering design.
- Permit Issued
- Issued on 6/14/2024
- Issuing Office
- Current Status
- CofO Issued on 12/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/12/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/15/2024 | ALFREDO JARA |
| Corrections Issued | 3/16/2024 | ALFREDO JARA |
| Plan Check Approved | 6/12/2024 | JOHNPAUL ISIP |
| Issued | 6/14/2024 | APPLICANT |
| CofO in Progress | 12/11/2025 | CHRISTOPHER ROJAS |
| Permit Finaled | 12/23/2025 | RUBEN SALAS |
| CofO Issued | 12/23/2025 | RUBEN SALAS |
| Permit Finaled | 12/23/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 3/30/2024 | BRYAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/2/2024 | BRYAN GODINEZ |
| Grading Pre-Inspection | Cleared | 4/4/2024 | CHARLES POWELL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/8/2024 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 8/12/2024 | Corrections Issued | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 8/19/2024 | Not Ready for Inspection | SEAN WIRCH |
| PLUMBING-Rough | 8/19/2024 | Corrections Issued | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2024 | Corrections Issued | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 8/22/2024 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 8/22/2024 | Partial Approval | JAVIER RAMOS JR |
| Sewer | 8/22/2024 | Partial Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 8/28/2024 | Partial Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2024 | Corrections Issued | JAVIER RAMOS JR |
| Deputy Wood Construction | 10/4/2024 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 10/8/2024 | Partial Inspection | JAVIER RAMOS JR |
| Deputy Drilled-In Anchors | 11/12/2024 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 11/15/2024 | Not Ready for Inspection | JAVIER RAMOS JR |
| Sewer | 11/15/2024 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 12/12/2024 | Corrections Issued | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 12/12/2024 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Rough | 1/16/2025 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 3/13/2025 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 3/13/2025 | Approved | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 3/13/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 3/13/2025 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 3/13/2025 | Partial Approval | JAVIER RAMOS JR |
| Insulation | 3/20/2025 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 3/25/2025 | Approved | JACK KARGODORIAN |
| Shower Pan | 4/28/2025 | Approved | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 5/15/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 5/20/2025 | Approved | CHRISTOPHER ROJAS |
| Gas Test | 7/23/2025 | Approved | NICHOLAS TROWBRIDGE |
| PLUMBING-Final | 7/23/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 9/29/2025 | Approved | CHRISTOPHER ROJAS |
| Final | 9/29/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Green Building Final | 9/29/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Rough | 9/29/2025 | Approved | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 9/29/2025 | SGSOV Approved | CHRISTOPHER ROJAS |
| Smoke Detectors | 9/29/2025 | Approved | CHRISTOPHER ROJAS |
| Final | 10/1/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Green Building Final | 10/1/2025 | Approved | CHRISTOPHER ROJAS |
| Final | 12/10/2025 | OK to Issue CofO | CHRISTOPHER ROJAS |