6730 N ROYER AVE 91307
Certificate Information: 6730 N ROYER AVE 91307
- Application / Permit
- 24014-20000-00894
- Plan Check / Job No.
- B24VN02947
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: Two story irregular shaped addition of 17' 11" x 16' 2 1/2" in the rear side of the SFD. All work done per engineer.
- Permit Issued
- Issued on 7/6/2024
- Issuing Office
- Current Status
- CofO Issued on 8/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/5/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/21/2024 | NAREG ATARIAN |
| Corrections Issued | 3/28/2024 | NAREG ATARIAN |
| Quality Review Completed | 3/29/2024 | OMID HEDAYAT |
| Plan Check Approved | 7/5/2024 | NAREG ATARIAN |
| Plan Check Approved | 7/6/2024 | NAREG ATARIAN |
| Issued | 7/6/2024 | APPLICANT |
| CofO in Progress | 8/12/2025 | TROY SANDERS |
| Permit Finaled | 8/26/2025 | JOHN JANSON |
| CofO Issued | 8/26/2025 | JOHN JANSON |
| Permit Finaled | 8/26/2025 | JOHN JANSON |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/12/2024 | EDGAR ALCARAZ |
| Watercourse | Cleared | 6/12/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/25/2024 | EDGAR ALCARAZ |
| Miscellaneous | Cleared | 6/25/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 6/25/2024 | EDGAR ALCARAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lobana,, Singh Maninder Pa; Lic. No.: C50989 | 885 PATRIOT DR #G MOORPARK, CA 93021 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/18/2024 | Not Ready for Inspection | TROY SANDERS |
| Footing/Foundation/Slab | 7/24/2024 | Approved | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2024 | Partial Approval | TROY SANDERS |
| Insulation | 8/1/2024 | Partial Approval | TROY SANDERS |
| PLUMBING-Rough | 8/1/2024 | Partial Approval | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 9/13/2024 | Partial Approval | TROY SANDERS |
| Interior/Exterior Lathing | 9/13/2024 | Not Ready for Inspection | TROY SANDERS |
| Wood Frame | 9/13/2024 | Not Ready for Inspection | TROY SANDERS |
| ELECTRICAL-Rough | 9/20/2024 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 9/20/2024 | Partial Approval | TROY SANDERS |
| Insulation | 9/30/2024 | Approved | TROY SANDERS |
| Drywall Nailing | 10/3/2024 | Approved | TROY SANDERS |
| Green Building Rough | 10/3/2024 | Approved | TROY SANDERS |
| Shower Pan | 10/16/2024 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 2/19/2025 | Approved | TROY SANDERS |
| Final | 2/19/2025 | No Access for Inspection | TROY SANDERS |
| Green Building Final | 2/19/2025 | No Access for Inspection | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 2/19/2025 | SGSOV Not Ready | TROY SANDERS |
| Smoke Detectors | 2/19/2025 | No Access for Inspection | TROY SANDERS |
| Final | 7/29/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| Green Building Final | 7/29/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| SGSOV-Seismic Gas S/O Valve | 7/29/2025 | SGSOV Not Ready | GEVORK IPCHYAN |
| Smoke Detectors | 7/29/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| Final | 8/11/2025 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 8/11/2025 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 8/11/2025 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 8/11/2025 | Approved | TROY SANDERS |