5218 N GOODLAND AVE 91607

Certificate Information: 5218 N GOODLAND AVE 91607

Application / Permit
24014-20000-00889
Plan Check / Job No.
B24VN02913
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: ENCLOSE 198 SF PORTION OF (E) REAR PATIO FOR BEDROOM TO (E) SFD, ALL WORK PER ENG.
Permit Issued
Issued on 3/20/2024
Issuing Office
Current Status
CofO Issued on 9/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/5/2024 APPLICANT
Assigned to Plan Check Engineer 3/7/2024 LUISANGEL VALENZUELA
Corrections Issued 3/8/2024 LUISANGEL VALENZUELA
Plan Check Approved 3/19/2024 LUISANGEL VALENZUELA
Issued 3/20/2024 APPLICANT
CofO in Progress 3/5/2025 OGANES TARAKHCHYAN
Permit Finaled 9/9/2025 RUBEN SALAS
CofO Issued 9/9/2025 RUBEN SALAS
Permit Finaled 9/9/2025 RUBEN SALAS

Permit Application Clearance Information

Specific Plan Cleared 3/12/2024 JOANNA MARROQUIN
ZI Cleared 3/12/2024 JOANNA MARROQUIN
ZI Cleared 3/12/2024 JOANNA MARROQUIN
Miscellaneous Cleared 3/13/2024 BRENNEN OBETO

Contact Information

Contractor Owner-Builder       ,
Engineer Grigoryan,, Souren; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 3/27/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 3/27/2024 Approved ROBERTO PALACIOS-LOPEZ
Rough-Elec/Plmb/HVAC 3/27/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Underground Mechanical 3/27/2024 Approved ROBERTO PALACIOS-LOPEZ
Deputy Drilled-In Anchors 4/1/2024 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 4/5/2024 Approved JOSE AVILA
Wood Frame 4/5/2024 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 4/9/2024 Corrections Issued JOSE AVILA
PLUMBING-Rough 4/9/2024 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 4/30/2024 Partial Approval JOSE AVILA
PLUMBING-Rough 4/30/2024 Approved JOSE AVILA
BUILDING-Rough-Frame 5/6/2024 Corrections Issued JOSE AVILA
Deputy Wood Construction 5/6/2024 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 5/8/2024 Approved JOHN COLEMAN
Interior/Exterior Lathing 5/8/2024 Approved JOHN COLEMAN
Insulation 5/13/2024 Approved JACK KARGODORIAN
Drywall Nailing 5/16/2024 Approved JOHN COLEMAN
Shower Pan 7/9/2024 Approved LEONARD ROSS II
Interior/Exterior Lathing 7/16/2024 Approved MICHEL ABAJAN
ELECTRICAL-Final 10/8/2024 Corrections Issued GAREN HAYRAPETYAN
PLUMBING-Final 10/8/2024 Approved GAREN HAYRAPETYAN
ELECTRICAL-Final 10/18/2024 Approved GAREN HAYRAPETYAN
Final 10/22/2024 Corrections Issued OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 10/22/2024 SGSOV Approved OGANES TARAKHCHYAN
Smoke Detectors 10/22/2024 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 12/30/2024 Not Ready for Inspection OGANES TARAKHCHYAN
Final 3/4/2025 OK to Issue CofO OGANES TARAKHCHYAN