14923 W DEVONSHIRE ST 91345
Certificate Information: 14923 W DEVONSHIRE ST 91345
- Application / Permit
- 24014-20000-00886
- Plan Check / Job No.
- B24VN02908
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED 2-CAR GARAGE TO ADU WITH ADDITION PER ORDINANCE AND LAMC 12.22 A33(c)&(d).
- Permit Issued
- Issued on 4/22/2024
- Issuing Office
- Current Status
- CofO Issued on 3/3/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/8/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/13/2024 | ZAW HAN |
| Corrections Issued | 3/14/2024 | ZAW HAN |
| Plan Check Approved | 4/13/2024 | ZAW HAN |
| Issued | 4/22/2024 | APPLICANT |
| CofO in Progress | 2/12/2026 | JENNIFER RABUCHIN |
| Permit Finaled | 3/3/2026 | RUBEN SALAS |
| CofO Issued | 3/3/2026 | RUBEN SALAS |
| Permit Finaled | 3/3/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/28/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 3/28/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 4/5/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 4/5/2024 | BIAINA HARITUNIAN |
Contact Information
| Architect | Hsu,, Peter Wu; Lic. No.: NA13798 | , |
| Contractor | Owner-Builder | , |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/5/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Deputy Drilled-In Anchors | 7/9/2024 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 7/19/2024 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 7/19/2024 | Partial Approval | JENNIFER RABUCHIN |
| Drywall Nailing | 11/13/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2024 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 11/13/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 2/5/2025 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 2/5/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 2/5/2025 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 2/5/2025 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 2/5/2025 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 2/13/2025 | Partial Approval | JENNIFER RABUCHIN |
| Insulation | 2/13/2025 | Approved | JENNIFER RABUCHIN |
| Special/Order Compliance | 2/13/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Drywall Nailing | 3/12/2025 | Approved | SALVADOR MARTINEZ |
| Green Building Rough | 3/12/2025 | Approved | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 1/12/2026 | Approved | MATTHEW NELSON |
| Final | 1/12/2026 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 1/12/2026 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 1/12/2026 | SGSOV Not Ready | MATTHEW NELSON |
| Smoke Detectors | 1/12/2026 | Approved | MATTHEW NELSON |
| Final | 1/23/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 1/23/2026 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 1/23/2026 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 1/23/2026 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 1/23/2026 | SGSOV Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 2/13/2026 | Approved | JENNIFER RABUCHIN |
| Final | 2/13/2026 | OK to Issue CofO | JENNIFER RABUCHIN |