3951 N ANASTASIA DR 91316
Certificate Information: 3951 N ANASTASIA DR 91316
- Application / Permit
- 24014-20000-00878
- Plan Check / Job No.
- B24VN02897
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Interior/Exterior remodel and multiple area additions on first and second stories of existing 2-story single family dwelling w/garage
- Permit Issued
- Issued on 5/21/2024
- Issuing Office
- Current Status
- CofO Issued on 4/18/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/5/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/7/2024 | VAHAN JIVALAGIAN |
| Corrections Issued | 3/10/2024 | VAHAN JIVALAGIAN |
| Quality Review Completed | 3/11/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 3/12/2024 | APPLICANT |
| Applicant returned to address corrections | 3/21/2024 | VAHAN JIVALAGIAN |
| Plan Check Approved | 5/20/2024 | VAHAN JIVALAGIAN |
| Issued | 5/21/2024 | APPLICANT |
| CofO in Progress | 1/22/2026 | SEAN WIRCH |
| Permit Finaled | 4/18/2026 | MICHAEL PELHAM |
| CofO Issued | 4/18/2026 | MICHAEL PELHAM |
| Permit Finaled | 4/18/2026 | MICHAEL PELHAM |
Permit Application Clearance Information
| ZA Case | Cleared | 4/12/2024 | DORIAN AGUILAR |
| Roof/Waste drainage to street | Cleared | 4/16/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 4/18/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 4/18/2024 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 5/11/2024 | KURT CORRAL |
| Grading Pre-Inspection | Cleared | 5/20/2024 | VAHAN JIVALAGIAN |
Contact Information
| Contractor | Revive Renovations Corp; Lic. No.: 1082167-B | 5939 PICKFORD ST LOS ANGELES, CA 90035 |
| Engineer | Dominguez,, Refugio; Lic. No.: C50820 | 254 COTTONWOOD ST ONTARIO, CA 91761 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 7/5/2024 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 7/11/2024 | Approved | JOHN KIDWELL |
| Deputy Steel/Welding | 7/26/2024 | Conditional Approval | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2024 | Approved | JOHN KIDWELL |
| PLUMBING-Rough | 10/31/2024 | Approved | JOHN KIDWELL |
| ELECTRICAL-Rough | 12/4/2024 | Approved | JOHN KIDWELL |
| HVAC-Rough | 12/4/2024 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 12/19/2024 | Partial Approval | JOHN KIDWELL |
| Green Building Rough | 12/19/2024 | Not Ready for Inspection | JOHN KIDWELL |
| BUILDING-Rough-Frame | 2/18/2025 | Approved | JOHN KIDWELL |
| Green Building Rough | 2/18/2025 | Approved | JOHN KIDWELL |
| Insulation | 2/18/2025 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 2/18/2025 | Partial Approval | JOHN KIDWELL |
| Drywall Nailing | 2/26/2025 | Approved | JOHN KIDWELL |
| Shower Pan | 2/26/2025 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 3/10/2025 | Partial Approval | JOHN KIDWELL |
| Final | 1/14/2026 | Not Ready for Inspection | JOHN KIDWELL |
| Green Building Final | 1/14/2026 | Approved | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 1/14/2026 | SGSOV Not Ready | JOHN KIDWELL |
| Smoke Detectors | 1/14/2026 | Approved | JOHN KIDWELL |
| ELECTRICAL-Final | 1/22/2026 | Approved | SEAN WIRCH |
| Final | 1/22/2026 | OK to Issue CofO | SEAN WIRCH |
| HVAC-Final | 1/22/2026 | Approved | SEAN WIRCH |
| PLUMBING-Final | 1/22/2026 | Approved | SEAN WIRCH |
| SGSOV-Seismic Gas S/O Valve | 1/22/2026 | SGSOV Approved | SEAN WIRCH |