120 1/2 W 77TH ST 90003
Certificate Information: 120 1/2 W 77TH ST 90003
- Application / Permit
- 24014-20000-00858
- Plan Check / Job No.
- B24VN02811
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan convert (e) 1-story garage and addition resulting in 1-story detached ADU per LAMC 12.22 A.33 (c)(d) R3 occupancy
- Permit Issued
- Issued on 10/10/2024
- Issuing Office
- Current Status
- CofO Issued on 12/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/6/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/8/2024 | KELVIN CHUONG |
| Corrections Issued | 3/10/2024 | KELVIN CHUONG |
| Applicant returned to address corrections | 4/22/2024 | KELVIN CHUONG |
| Applicant returned to address corrections | 9/18/2024 | JOSE VELAZQUEZ |
| Plan Check Approved | 10/10/2024 | JOSE VELAZQUEZ |
| Issued | 10/10/2024 | APPLICANT |
| CofO in Progress | 12/10/2025 | JOHN QUINTANILLA |
| Permit Finaled | 12/11/2025 | DEROLD HAUFF |
| CofO Issued | 12/11/2025 | DEROLD HAUFF |
| Permit Finaled | 12/11/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/11/2024 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/15/2024 | DAVID LOPEZ |
| Sewer availability | Cleared | 4/15/2024 | DAVID LOPEZ |
| Low Impact Development (LID) | Cleared | 9/3/2024 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 9/5/2024 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/8/2024 | Corrections Issued | MICHAEL LEWIS |
| Deputy Drilled-In Anchors | 11/12/2024 | Conditional Approval | ANTHONY RAMOS |
| Footing/Foundation/Slab | 11/14/2024 | Corrections Issued | MICHAEL LEWIS |
| Underground Mechanical | 11/14/2024 | Approved | MICHAEL LEWIS |
| Pre-Inspection | 2/12/2025 | Partial Inspection | JOHN QUINTANILLA |
| Footing/Foundation/Slab | 2/18/2025 | Partial Approval | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 3/21/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2025 | Partial Approval | JOHN QUINTANILLA |
| Green Building Rough | 3/21/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 4/14/2025 | No Access for Inspection | JOHN QUINTANILLA |
| PLUMBING-Rough | 4/14/2025 | No Access for Inspection | JOHN QUINTANILLA |
| Wood Frame | 4/14/2025 | No Access for Inspection | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 4/17/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 4/17/2025 | Corrections Issued | JOHN QUINTANILLA |
| Green Building Rough | 4/17/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| PLUMBING-Rough | 4/17/2025 | Corrections Issued | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 4/23/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 4/23/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Green Building Rough | 4/23/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| PLUMBING-Rough | 4/23/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 5/7/2025 | Corrections Issued | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 5/7/2025 | Approved | JOHN QUINTANILLA |
| Green Building Rough | 5/7/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| PLUMBING-Rough | 5/7/2025 | Approved | JOHN QUINTANILLA |
| Insulation | 5/14/2025 | Conditional Approval | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 5/14/2025 | Corrections Issued | JOHN QUINTANILLA |
| Insulation | 5/20/2025 | Approved | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 5/20/2025 | Approved | JOHN QUINTANILLA |
| Drywall Nailing | 6/2/2025 | Approved | ANTHONY RAMOS |
| Green Building Rough | 6/2/2025 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 6/24/2025 | Approved | ANTHONY RAMOS |
| Shower Pan | 6/24/2025 | Approved | ANTHONY RAMOS |
| BUILDING-Rough-Frame | 9/15/2025 | No Access for Inspection | JOHN QUINTANILLA |
| Final | 9/15/2025 | No Access for Inspection | JOHN QUINTANILLA |
| Footing/Foundation/Slab | 9/15/2025 | No Access for Inspection | JOHN QUINTANILLA |
| Green Building Final | 9/15/2025 | No Access for Inspection | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 9/15/2025 | SGSOV Not Ready | JOHN QUINTANILLA |
| Smoke Detectors | 9/15/2025 | No Access for Inspection | JOHN QUINTANILLA |
| Pre-Inspection | 9/17/2025 | Partial Inspection | JOHN QUINTANILLA |
| Final | 9/19/2025 | Corrections Issued | JEFFREY MEAD |
| Green Building Final | 9/19/2025 | Not Ready for Inspection | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 9/19/2025 | SGSOV Not Ready | JEFFREY MEAD |
| Smoke Detectors | 9/19/2025 | Not Ready for Inspection | JEFFREY MEAD |
| BUILDING-Rough-Frame | 9/24/2025 | Approved | JOHN QUINTANILLA |
| Final | 9/24/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Footing/Foundation/Slab | 9/24/2025 | Approved | JOHN QUINTANILLA |
| Green Building Final | 9/24/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 9/24/2025 | SGSOV Not Ready | JOHN QUINTANILLA |
| Smoke Detectors | 9/24/2025 | Approved | JOHN QUINTANILLA |
| Final | 11/18/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Green Building Final | 11/18/2025 | Approved | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 11/18/2025 | SGSOV Not Ready | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 11/21/2025 | SGSOV Approved | JOHN QUINTANILLA |
| Final | 12/1/2025 | OK to Issue CofO | JOHN QUINTANILLA |