16438-16440 W DONMETZ ST 91344
Certificate Information: 16438-16440 W DONMETZ ST 91344
- Application / Permit
- 24014-20000-00857
- Plan Check / Job No.
- B24VN02810
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 23'-9" X 12'-7" ADDITION TO (E) SFD AND CONVERT (E) ATTACHED GARAGE TO (N) JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) and 65852.22.
- Permit Issued
- Issued on 5/23/2024
- Issuing Office
- Current Status
- CofO Issued on 12/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/5/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/8/2024 | ISIS ARGUETA |
| Corrections Issued | 3/11/2024 | ISIS ARGUETA |
| Applicant returned to address corrections | 4/17/2024 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 4/27/2024 | ALEC MOUSAKHANIAN |
| Issued | 5/23/2024 | APPLICANT |
| CofO in Progress | 11/12/2024 | JAVIER RAMOS JR |
| Permit Finaled | 12/17/2024 | RUBEN SALAS |
| CofO Issued | 12/17/2024 | RUBEN SALAS |
| Permit Finaled | 12/17/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Hold | Cleared | 3/22/2024 | TERESA RIVAS |
| Grading Pre-Inspection | Cleared | 4/2/2024 | CHARLES POWELL |
| Address approval | Cleared | 4/3/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 4/3/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 4/3/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 4/8/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Gutierrez Brother Builders Inc; Lic. No.: 1057968-B | , |
| Engineer | Nguyen,, Quynh Anh; Lic. No.: NA58592 | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/12/2024 | Partial Approval | JAVIER RAMOS JR |
| Deputy Drilled-In Anchors | 6/13/2024 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 6/18/2024 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 8/6/2024 | Partial Inspection | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 8/6/2024 | Partial Approval | JAVIER RAMOS JR |
| Green Building Rough | 8/6/2024 | Not Ready for Inspection | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 8/22/2024 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 8/22/2024 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 8/22/2024 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 8/22/2024 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 8/22/2024 | Approved | JAVIER RAMOS JR |
| MERV13>=Rough | 8/22/2024 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 8/22/2024 | Approved | JAVIER RAMOS JR |
| Shower Pan | 8/22/2024 | Approved | JAVIER RAMOS JR |
| Insulation | 9/19/2024 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 9/23/2024 | Partial Approval | SALVADOR MARTINEZ |
| Drywall Nailing | 9/26/2024 | Approved | JAVIER RAMOS JR |
| Insulation | 9/26/2024 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 11/7/2024 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 11/7/2024 | Approved | JAVIER RAMOS JR |
| Final | 11/7/2024 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 11/7/2024 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 11/7/2024 | Approved | JAVIER RAMOS JR |
| MERV13>=Final | 11/7/2024 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 11/7/2024 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 11/7/2024 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 11/7/2024 | Approved | JAVIER RAMOS JR |
| Final | 11/12/2024 | OK to Issue CofO | JAVIER RAMOS JR |
| Service/Power Release | 11/12/2024 | Approved | JAVIER RAMOS JR |