5632 N ALLOTT AVE 91401

Certificate Information: 5632 N ALLOTT AVE 91401

Application / Permit
24014-20000-00841
Plan Check / Job No.
B24VN02750
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE (E) COVERED PATIO. ADD 2' X 9'-7" COVERED PORCH. 35' X 35'-2" IRREG SHAPED ADDITION FOR NEW BEDROOM AND BATHROOM, AND TO ENLARGE FAMILY ROOM. REMODEL KITCHEN. **NFPA 13D FIRE SPRINKELRS REQUIRED**
Permit Issued
Issued on 4/11/2024
Issuing Office
Valley
Current Status
CofO Issued on 2/3/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/1/2024 APPLICANT
Assigned to Plan Check Engineer 3/7/2024 JEROME MAGAT PALMA
Corrections Issued 3/9/2024 JEROME MAGAT PALMA
Building Plans Picked Up 3/11/2024 APPLICANT
Plan Check Approved 4/11/2024 ISIS ARGUETA
Issued 4/11/2024 APPLICANT
CofO in Progress 1/22/2026 RYAN SALAZAR
Permit Finaled 2/3/2026 RUBEN SALAS
Permit Finaled 2/3/2026 RUBEN SALAS
CofO Issued 2/3/2026 RUBEN SALAS

Permit Application Clearance Information

Low Impact Development (LID) Cleared 3/29/2024 TOMMY YIN
Roof/Waste drainage to street Cleared 4/5/2024 BRYAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 4/9/2024 BRYAN GODINEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Yeghiayan,, Armond; Lic. No.: C69935 16873 MCKEEVER ST      GRANADA HILLS, CA 91344

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/22/2024 Corrections Issued RYAN SALAZAR
Deputy Drilled-In Anchors 5/24/2024 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 5/30/2024 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 6/7/2024 Partial Approval RYAN SALAZAR
Green Building Rough 6/7/2024 Not Ready for Inspection RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 6/10/2024 Partial Approval RYAN SALAZAR
ELECTRICAL-Rough 9/3/2024 Not Ready for Inspection RYAN SALAZAR
PLUMBING-Rough 9/3/2024 Not Ready for Inspection RYAN SALAZAR
ELECTRICAL-Rough 9/5/2024 Approved RYAN SALAZAR
HVAC-Rough 9/5/2024 Approved RYAN SALAZAR
PLUMBING-Rough 9/5/2024 Partial Approval RYAN SALAZAR
Deputy Drilled-In Anchors 9/6/2024 Conditional Approval ROBERT GOLD
Insulation 10/28/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 10/28/2024 Partial Approval RYAN SALAZAR
Drywall Nailing 11/4/2024 Approved RYAN SALAZAR
Shower Pan 12/10/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 12/18/2024 Approved JENNIFER RABUCHIN
Drywall Nailing 6/4/2025 No Access for Inspection RYAN SALAZAR
Interior/Exterior Lathing 6/4/2025 No Access for Inspection RYAN SALAZAR
BUILDING-Rough-Frame 12/26/2025 Approved RYAN SALAZAR
Final 12/26/2025 Corrections Issued RYAN SALAZAR
Green Building Final 12/26/2025 Approved RYAN SALAZAR
Green Building Rough 12/26/2025 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 12/26/2025 SGSOV Approved RYAN SALAZAR
Smoke Detectors 12/26/2025 Approved RYAN SALAZAR
Final 1/22/2026 OK to Issue CofO RYAN SALAZAR