5848 N TEXHOMA AVE 91316
Certificate Information: 5848 N TEXHOMA AVE 91316
- Application / Permit
- 24014-20000-00830
- Plan Check / Job No.
- B24VN02712
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- IRR SHAPED 44' X 23'-9" ADDITION AT REAR OF EXISTING 1-STORY SFD W/ ATT 1-CAR GARAGE. INT REMODEL AND REPLACE EXISTING WINDOWS & DOORS PER PLAN. ADD 10'-6" X 18 COVERED PATIO COVER. <NFPA 13D FIRE SPRINKLER THRU-OUT>
- Permit Issued
- Issued on 7/18/2024
- Issuing Office
- Valley
- Current Status
- Issued on 7/18/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/29/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/6/2024 | HAYATO TSUCHIYA |
| Corrections Issued | 3/6/2024 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 3/13/2024 | APPLICANT |
| Plan Check Approved | 7/18/2024 | ISIS ARGUETA |
| Issued | 7/18/2024 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/11/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 4/11/2024 | CARLOS AGUILERA |
| ZI | Cleared | 5/3/2024 | JASON CHAN |
| Low Impact Development (LID) | Cleared | 6/27/2024 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 7/2/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Benedetti Bryan A; Lic. No.: 572284-B | 17912 TIARA ST ENCINO, CA 91316 |
| Engineer | Vasquez,, Luis Fernando; Lic. No.: C56232 | 375 LA MIRADA AVENUE SAN MARINO, CA 91108 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/9/2024 | Conditional Approval | MORRIS JACKSON |
| Footing/Foundation/Slab | 10/4/2024 | Corrections Issued | MORRIS JACKSON |
| Footing/Foundation/Slab | 10/9/2024 | Approved | MORRIS JACKSON |
| ELECTRICAL-Rough | 11/20/2024 | Partial Approval | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/20/2024 | Partial Approval | MORRIS JACKSON |
| Gas Test | 11/20/2024 | Partial Approval | MORRIS JACKSON |
| Green Building Rough | 11/20/2024 | Not Ready for Inspection | MORRIS JACKSON |
| PLUMBING-Rough | 11/20/2024 | Partial Approval | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/25/2024 | Partial Approval | MORRIS JACKSON |
| Insulation | 11/25/2024 | Partial Approval | MORRIS JACKSON |
| Sewer | 11/25/2024 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 5/1/2025 | Corrections Issued | MORRIS JACKSON |
| ELECTRICAL-Rough | 5/1/2025 | Approved | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2025 | Partial Approval | MORRIS JACKSON |
| Green Building Rough | 5/1/2025 | Not Ready for Inspection | MORRIS JACKSON |
| HVAC-Rough | 5/1/2025 | Approved | MORRIS JACKSON |
| PLUMBING-Rough | 5/1/2025 | Approved | MORRIS JACKSON |
| Verify Sprinkler Sign Off | 5/1/2025 | Corrections Issued | MORRIS JACKSON |
| Drywall Nailing | 6/12/2025 | Not Ready for Inspection | MORRIS JACKSON |
| Green Building Rough | 6/12/2025 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 6/12/2025 | Partial Approval | MORRIS JACKSON |
| Drywall Nailing | 6/13/2025 | Partial Approval | MORRIS JACKSON |
| Deputy Wood Construction | 6/27/2025 | Conditional Approval | MORRIS JACKSON |