1416 E 51ST ST 90011
Certificate Information: 1416 E 51ST ST 90011
- Application / Permit
- 24014-20000-00819
- Plan Check / Job No.
- B24VN02654
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AND REMODEL TO EX. SFD. REFRAME FRONT PORTION OF SFD. WORK PER DESIGN. AUTOMATIC FIRE SPRINKLER SYSTEM REQUIRED.
- Permit Issued
- Issued on 3/31/2024
- Issuing Office
- Current Status
- CofO Issued on 1/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/2/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/7/2024 | ROSENDO MEDINA |
| Corrections Issued | 3/8/2024 | ROSENDO MEDINA |
| Plan Check Approved | 3/29/2024 | ROSENDO MEDINA |
| Issued | 3/31/2024 | APPLICANT |
| CofO in Progress | 1/8/2025 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 1/9/2025 | DEROLD HAUFF |
| Permit Finaled | 1/9/2025 | DEROLD HAUFF |
| CofO Issued | 1/9/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 3/16/2024 | JESSICA OPINION |
| Eng Process Fee Ord 176,300 | Cleared | 3/21/2024 | JESSICA OPINION |
| Tenant Habitability Plan | Cleared | 3/22/2024 | HUGO GARRIDO GARZA |
Contact Information
| Architect | Di, Zitti, Fernando; Lic. No.: NA24587 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/20/2024 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 6/25/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 6/28/2024 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 7/9/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 7/9/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 7/9/2024 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 7/9/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 7/11/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 7/11/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 7/16/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 7/17/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 7/17/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Deputy Drilled-In Anchors | 8/7/2024 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/16/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Green Building Rough | 8/16/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 8/16/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 8/27/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 8/27/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 8/27/2024 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 8/27/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 8/27/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 10/2/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 10/2/2024 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 10/2/2024 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 10/2/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 10/2/2024 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 10/2/2024 | Approved | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 10/2/2024 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 10/4/2024 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 10/9/2024 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 10/9/2024 | Approved | JOSH MEISTER |
| ELECTRICAL-Final | 12/19/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 12/19/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 12/19/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 12/19/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 12/19/2024 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 12/19/2024 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 12/19/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 12/30/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 12/30/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 12/30/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 12/30/2024 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 12/30/2024 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Final | 1/7/2025 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| Green Building Final | 1/7/2025 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 1/7/2025 | Approved | ALEJANDRO DE ARTOLA |