4514-4514 1/2 S 9TH AVE 90043
Certificate Information: 4514-4514 1/2 S 9TH AVE 90043
- Application / Permit
- 24014-20000-00816
- Plan Check / Job No.
- B24VN02648
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- ADD 32'-8" X 24' TWO STORY TO EXISTING SINGLE FAMILY DWELLING AND CONVERT TO NEW DUPLEX; EQUIPPED WITH NFPA 13D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 11/12/2024
- Issuing Office
- Current Status
- CofO Issued on 5/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/28/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/7/2024 | SELLA BENYAMIN |
| Corrections Issued | 3/12/2024 | SELLA BENYAMIN |
| Quality Review Completed | 3/18/2024 | STEVEN KIM |
| Building Plans Picked Up | 3/19/2024 | APPLICANT |
| Plan Check Approved | 11/12/2024 | SELLA BENYAMIN |
| Issued | 11/12/2024 | APPLICANT |
| CofO in Progress | 4/29/2025 | LUIS CASTRO |
| Permit Finaled | 5/3/2025 | DEROLD HAUFF |
| CofO Issued | 5/3/2025 | DEROLD HAUFF |
| Permit Finaled | 5/3/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/7/2024 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 6/10/2024 | CELINA MORENO |
| Sewer availability | Cleared | 6/10/2024 | CELINA MORENO |
| Miscellaneous | Cleared | 6/12/2024 | DALIA MOKAYED |
| Hydrant and Access approval | Cleared | 7/22/2024 | KURT CORRAL |
| Low Impact Development (LID) | Cleared | 10/24/2024 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 10/30/2024 | CELINA MORENO |
Contact Information
| Architect | Saunders,, Niall F; Lic. No.: C26955 | 2700 WEST COAST HIGHWAY SUITE 200 NEWPORT BEACH, CA 92663 |
| Contractor | Owner-Builder | , |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/20/2024 | Corrections Issued | BARRY HACHE |
| Excavation/Setback/Form/Re-Bar | 11/23/2024 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 11/23/2024 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2024 | Partial Approval | BARRY HACHE |
| Green Building Rough | 12/2/2024 | Not Ready for Inspection | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2024 | Partial Approval | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 12/30/2024 | Partial Approval | NICHOLAS LOPEZ |
| Underground Mechanical | 12/30/2024 | Partial Approval | NICHOLAS LOPEZ |
| HVAC-Rough | 1/7/2025 | Approved | LUIS CASTRO |
| PLUMBING-Rough | 1/7/2025 | Approved | LUIS CASTRO |
| ELECTRICAL-Rough | 1/10/2025 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 1/16/2025 | Partial Approval | LUIS CASTRO |
| Green Building Rough | 1/16/2025 | Approved | LUIS CASTRO |
| Interior/Exterior Lathing | 1/16/2025 | Partial Inspection | LUIS CASTRO |
| Insulation | 1/21/2025 | Corrections Issued | ALEX COLIN |
| Interior/Exterior Lathing | 1/21/2025 | Approved | ALEX COLIN |
| Shower Pan | 1/21/2025 | Approved | ALEX COLIN |
| Drywall Nailing | 1/24/2025 | Conditional Approval | ALEX COLIN |
| ELECTRICAL-Final | 4/24/2025 | Approved | LUIS CASTRO |
| Final | 4/24/2025 | Corrections Issued | LUIS CASTRO |
| HVAC-Final | 4/24/2025 | Approved | LUIS CASTRO |
| PLUMBING-Final | 4/24/2025 | Approved | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 4/24/2025 | SGSOV Approved | LUIS CASTRO |
| ELECTRICAL-Final | 4/28/2025 | Approved | LUIS CASTRO |
| Final | 4/28/2025 | Corrections Issued | LUIS CASTRO |
| BUILDING-Rough-Frame | 4/29/2025 | Approved | LUIS CASTRO |
| Final | 4/29/2025 | OK to Issue CofO | LUIS CASTRO |
| Footing/Foundation/Slab | 4/29/2025 | Approved | LUIS CASTRO |
| Green Building Final | 4/29/2025 | Approved | LUIS CASTRO |
| Smoke Detectors | 4/29/2025 | Approved | LUIS CASTRO |