18138 W ECCLES ST 91325

Certificate Information: 18138 W ECCLES ST 91325

Application / Permit
24014-20000-00812
Plan Check / Job No.
B24VN02642
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE (411.75 SF) WITH 20'-4" x 22'-2 1/2" (429.45 SF) ADDITION AND 10'-6" x 20'-4" (127.06 SF) IRREG. SHAPED ADDITION TO A NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). REMOVE (E) SERVICE ROOM.
Permit Issued
Issued on 8/28/2024
Issuing Office
Current Status
CofO Issued on 4/29/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/1/2024 APPLICANT
Assigned to Plan Check Engineer 3/6/2024 GIOVANNY CHAVEZ
Corrections Issued 3/7/2024 GIOVANNY CHAVEZ
Applicant returned to address corrections 8/2/2024 GIOVANNY CHAVEZ
Applicant returned to address corrections 8/13/2024 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 8/22/2024 MIROOSH KHACHATOORIAN
Plan Check Approved 8/26/2024 MIROOSH KHACHATOORIAN
Issued 8/28/2024 APPLICANT
CofO in Progress 2/2/2026 KRISTEN CAUSEY
Permit Finaled 4/29/2026 JOHN JANSON
CofO Issued 4/29/2026 JOHN JANSON
Permit Finaled 4/29/2026 JOHN JANSON

Permit Application Clearance Information

Low Impact Development (LID) Cleared 7/2/2024 LUIS LUVANO
Construction near power lines Cleared 7/18/2024 RIDWAN HARDY
Construction within easement Cleared 7/18/2024 RIDWAN HARDY
Address approval Cleared 7/22/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 7/22/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 7/25/2024 BIAINA HARITUNIAN
Sewer availability Cleared 7/25/2024 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/22/2024 Partial Inspection KRISTEN CAUSEY
Pre-Inspection 10/28/2024 Partial Approval TROY SANDERS
PLUMBING-Rough 12/5/2024 Partial Approval GEVORK IPCHYAN
Underground Mechanical 12/5/2024 Partial Approval GEVORK IPCHYAN
Deputy Drilled-In Anchors 12/10/2024 Conditional Approval HENRY KIM
Footing/Foundation/Slab 12/11/2024 Not Ready for Inspection KRISTEN CAUSEY
PLUMBING-Rough 12/11/2024 Partial Approval KRISTEN CAUSEY
Footing/Foundation/Slab 12/12/2024 Approved KRISTEN CAUSEY
Floor/Roof Diaphrgm/Shear Wall 1/17/2025 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 1/29/2025 Not Ready for Inspection KRISTEN CAUSEY
Interior/Exterior Lathing 2/5/2025 Partial Approval KRISTEN CAUSEY
PLUMBING-Rough 2/12/2025 Approved KRISTEN CAUSEY
ELECTRICAL-Rough 2/21/2025 Approved KRISTEN CAUSEY
Wood Frame 3/3/2025 Not Ready for Inspection KRISTEN CAUSEY
Insulation 3/10/2025 Partial Inspection KRISTEN CAUSEY
Drywall Nailing 3/17/2025 Not Ready for Inspection KRISTEN CAUSEY
BUILDING-Rough-Frame 3/19/2025 Approved KRISTEN CAUSEY
Green Building Rough 3/19/2025 Approved KRISTEN CAUSEY
Drywall Nailing 3/21/2025 Approved KRISTEN CAUSEY
Insulation 3/21/2025 Approved KRISTEN CAUSEY
Shower Pan 5/5/2025 Approved DAVID SCANTLIN
Shower Pan 5/13/2025 Approved KRISTEN CAUSEY
Pre-Inspection 5/15/2025 Partial Inspection KRISTEN CAUSEY
ELECTRICAL-Final 8/18/2025 Approved KRISTEN CAUSEY
ELECTRICAL-Final 10/30/2025 Approved KRISTEN CAUSEY
Final 10/30/2025 Corrections Issued KRISTEN CAUSEY
Green Building Final 10/30/2025 Not Ready for Inspection KRISTEN CAUSEY
HVAC-Final 10/30/2025 Approved KRISTEN CAUSEY
PLUMBING-Final 10/30/2025 Approved KRISTEN CAUSEY
SGSOV-Seismic Gas S/O Valve 10/30/2025 SGSOV Not Ready KRISTEN CAUSEY
Smoke Detectors 10/30/2025 Not Ready for Inspection KRISTEN CAUSEY
Final 11/18/2025 Not Ready for Inspection KRISTEN CAUSEY
Green Building Final 11/18/2025 Not Ready for Inspection KRISTEN CAUSEY
SGSOV-Seismic Gas S/O Valve 11/18/2025 SGSOV Not Ready KRISTEN CAUSEY
Smoke Detectors 11/18/2025 Approved KRISTEN CAUSEY
Final 12/5/2025 Not Ready for Inspection DAVID SCANTLIN
Green Building Final 12/5/2025 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 12/5/2025 SGSOV Approved DAVID SCANTLIN
Final 1/14/2026 Not Ready for Inspection KRISTEN CAUSEY
Final 1/28/2026 OK to Issue CofO KRISTEN CAUSEY
Service/Power Release 1/28/2026 Approved KRISTEN CAUSEY