6100 N SEPULVEDA BLVD 91411

Certificate Information: 6100 N SEPULVEDA BLVD 91411

Application / Permit
24014-20000-00807
Plan Check / Job No.
B23VN18048
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(23) Miscellaneous Bldg/Structure
Work Description
New prefabricated fleet restroom next to the existing one-story building.
Permit Issued
Issued on 10/18/2024
Issuing Office
Current Status
CofO Issued on 7/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/28/2024 APPLICANT
Assigned to Zoning Architect 2/29/2024 ARSALAN SHABESTARI
Assigned to Plan Check Engineer 2/29/2024 ARSALAN SHABESTARI
Corrections Issued 3/2/2024 ARSALAN SHABESTARI
Quality Review Completed 3/19/2024 YOUNG KIM
Applicant returned to address corrections 6/15/2024 ARSALAN SHABESTARI
Applicant returned to address corrections 7/13/2024 ARSALAN SHABESTARI
Plan Check Approved 10/7/2024 ARSALAN SHABESTARI
Issued 10/18/2024 APPLICANT
CofO in Progress 7/9/2025 ROBERT DAVIS
Permit Finaled 7/9/2025 JEFFREY DURAN
CofO Issued 7/9/2025 JEFFREY DURAN
Permit Finaled 7/9/2025 JEFFREY DURAN

Permit Application Clearance Information

Metro Rail approval Cleared 4/29/2024 JENNIFER SU
ZA Case Cleared 5/2/2024 ALEX VELA
Roof/Waste drainage to street Cleared 5/4/2024 CARLOS AGUILERA
Sewer availability Cleared 5/4/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 5/6/2024 CARLOS AGUILERA
Tract Map conditions Cleared 5/8/2024 ALEX VELA
Tract Map conditions Cleared 5/8/2024 ALEX VELA
Tract Map conditions Cleared 5/8/2024 ALEX VELA
Tract Map conditions Cleared 5/8/2024 ALEX VELA
Tract Map conditions Cleared 5/8/2024 ALEX VELA
Tract Map conditions Cleared 5/8/2024 ALEX VELA
ZI Cleared 5/8/2024 ALEX VELA
Zoning Plan Check Cleared 8/6/2024 Shangqin Xie
Green Code Cleared 8/28/2024 MICHAEL AYERS
DAS Clearance Cleared 9/18/2024 Shangqin Xie

Contact Information

Contractor Harvey Usa Llc; Lic. No.: 866177-B       ,

Inspector Information

ROBERT DAVIS, (818) 374-1125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/16/2025 Approved ROBERT DAVIS
Reinforced Concrete Frame 1/24/2025 Partial Approval ROBERT DAVIS
Final 2/12/2025 Not Ready for Inspection ROBERT DAVIS
Final 7/9/2025 OK to Issue CofO ROBERT DAVIS
Footing/Foundation/Slab 7/9/2025 Approved ROBERT DAVIS
Green Building Final 7/9/2025 Approved ROBERT DAVIS
Green Building Rough 7/9/2025 Approved ROBERT DAVIS
METHANE-Barrier 7/9/2025 Approved ROBERT DAVIS
METHANE-Final 7/9/2025 Approved ROBERT DAVIS
METHANE-Rough 7/9/2025 Approved ROBERT DAVIS
METHANE-Subgrade 7/9/2025 Approved ROBERT DAVIS
SGSOV-Seismic Gas S/O Valve 7/9/2025 SGSOV No Gas ROBERT DAVIS
Smoke Detectors 7/9/2025 Approved ROBERT DAVIS
Verify Sprinkler Sign Off 7/9/2025 Approved ROBERT DAVIS
Wood Frame 7/9/2025 Approved ROBERT DAVIS