17210 W BALTAR ST 91406

Certificate Information: 17210 W BALTAR ST 91406

Application / Permit
24014-20000-00791
Plan Check / Job No.
B24VN02567
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 24.75' X 22.25' & 7.5' X 5.083' IRREGUILAR SHAPE ADDITION TO (E) SFD USING WOOD FRAME PRESCRIPTIVE PROVISION
Permit Issued
Issued on 3/5/2024
Issuing Office
Current Status
CofO Issued on 9/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/27/2024 APPLICANT
Assigned to Plan Check Engineer 2/27/2024 ARAMIK SHAHMIRZAIAN
Corrections Issued 2/27/2024 ARAMIK SHAHMIRZAIAN
Applicant returned to address corrections 3/1/2024 DANIEL ABRAMYAN
Plan Check Approved 3/5/2024 ALEC MOUSAKHANIAN
Issued 3/5/2024 APPLICANT
CofO in Progress 8/21/2024 RAUL OLAGI
Permit Finaled 9/5/2024 DANIEL ORRANTE
CofO Issued 9/5/2024 DANIEL ORRANTE
Permit Finaled 9/5/2024 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/29/2024 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 2/29/2024 EDGAR ALCARAZ
Sewer availability Cleared 2/29/2024 EDGAR ALCARAZ
Low Impact Development (LID) Cleared 3/5/2024 ROGELIO CORTES

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/27/2024 Approved SALVADOR MARTINEZ
Footing/Foundation/Slab 3/27/2024 Approved SALVADOR MARTINEZ
Sewer 3/27/2024 Approved SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 4/1/2024 Not Ready for Inspection KEVIN BERBERYAN
Insulation 4/1/2024 Partial Approval KEVIN BERBERYAN
Sewer 4/1/2024 Partial Inspection KEVIN BERBERYAN
BUILDING-Rough-Frame 4/2/2024 Not Ready for Inspection SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 4/2/2024 Approved SALVADOR MARTINEZ
Green Building Rough 4/2/2024 Not Ready for Inspection SALVADOR MARTINEZ
Insulation 4/2/2024 Partial Inspection SALVADOR MARTINEZ
PLUMBING-Rough 4/2/2024 Not Ready for Inspection SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 4/3/2024 Approved SALVADOR MARTINEZ
ELECTRICAL-Rough 4/4/2024 Approved SALVADOR MARTINEZ
Interior/Exterior Lathing 4/4/2024 Partial Approval SALVADOR MARTINEZ
PLUMBING-Rough 4/4/2024 Corrections Issued SALVADOR MARTINEZ
BUILDING-Rough-Frame 4/9/2024 Partial Approval SALVADOR MARTINEZ
Green Building Rough 4/9/2024 Not Ready for Inspection SALVADOR MARTINEZ
HVAC-Rough 4/9/2024 Approved SALVADOR MARTINEZ
PLUMBING-Rough 4/9/2024 Approved SALVADOR MARTINEZ
Shower Pan 4/9/2024 Approved SALVADOR MARTINEZ
Insulation 4/11/2024 Approved SALVADOR MARTINEZ
Drywall Nailing 4/15/2024 Approved SALVADOR MARTINEZ
ELECTRICAL-Final 5/13/2024 Corrections Issued SALVADOR MARTINEZ
HVAC-Final 5/13/2024 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Final 5/13/2024 Approved SALVADOR MARTINEZ
ELECTRICAL-Final 7/5/2024 Approved SALVADOR MARTINEZ
Green Building Final 7/5/2024 Approved SALVADOR MARTINEZ
HVAC-Final 7/5/2024 Approved SALVADOR MARTINEZ
PLUMBING-Final 7/5/2024 Approved SALVADOR MARTINEZ
BUILDING-Rough-Frame 8/20/2024 Approved RAUL OLAGI
Final 8/20/2024 OK to Issue CofO RAUL OLAGI
Green Building Rough 8/20/2024 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 8/20/2024 SGSOV Approved RAUL OLAGI
Smoke Detectors 8/20/2024 Approved RAUL OLAGI