4943 N PALOMAR DR 91356
Certificate Information: 4943 N PALOMAR DR 91356
- Application / Permit
- 24014-20000-00754
- Plan Check / Job No.
- B24VN02468
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Convert portions of patios and porches to the SFD, remodel the SFD and addition to the SFD. All work done per engineer.
- Permit Issued
- Issued on 4/18/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/24/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/23/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/29/2024 | NAREG ATARIAN |
| Corrections Issued | 3/2/2024 | NAREG ATARIAN |
| Quality Review Completed | 3/6/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 3/7/2024 | APPLICANT |
| Plan Check Approved | 4/18/2024 | NAREG ATARIAN |
| Issued | 4/18/2024 | APPLICANT |
| CofO in Progress | 2/13/2025 | JOHN KIDWELL |
| CofO Issued | 3/24/2025 | JOHN JANSON |
| Permit Finaled | 3/24/2025 | JOHN JANSON |
Permit Application Clearance Information
| Sewer availability | Cleared | 3/9/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/11/2024 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 3/11/2024 | LEE GUILBEAUX |
| Low Impact Development (LID) | Cleared | 3/19/2024 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 3/19/2024 | CARLOS RAMIREZ |
| Hydrant and Access approval | Cleared | 4/12/2024 | RUEL COLE |
| Grading Pre-Inspection | Cleared | 4/18/2024 | ROBERT PINA |
Contact Information
| Contractor | Finesse Remodeling & Consulting Inc; Lic. No.: 932094-B | 4600 ARIBA DRIVE TARZANA, CA 91356 |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/10/2024 | Conditional Approval | HENRY KIM |
| Underground Mechanical | 5/13/2024 | Approved | MORRIS JACKSON |
| Footing/Foundation/Slab | 5/15/2024 | Corrections Issued | JOHN KIDWELL |
| Footing/Foundation/Slab | 5/20/2024 | Approved | JOHN KIDWELL |
| Deputy Wood Construction | 6/3/2024 | Corrections Issued | JOHN KIDWELL |
| Deputy Wood Construction | 6/5/2024 | Corrections Issued | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2024 | Partial Approval | JOHN KIDWELL |
| ELECTRICAL-Rough | 6/26/2024 | Approved | JOHN KIDWELL |
| HVAC-Rough | 6/26/2024 | Approved | JOHN KIDWELL |
| PLUMBING-Rough | 6/26/2024 | Approved | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2024 | Partial Approval | JOHN KIDWELL |
| Green Building Rough | 7/10/2024 | Not Ready for Inspection | JOHN KIDWELL |
| BUILDING-Rough-Frame | 7/26/2024 | Partial Approval | MORRIS JACKSON |
| Insulation | 7/26/2024 | Approved | MORRIS JACKSON |
| Shower Pan | 7/26/2024 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 8/6/2024 | Approved | JOHN KIDWELL |
| Drywall Nailing | 8/6/2024 | Approved | JOHN KIDWELL |
| Green Building Rough | 8/6/2024 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 8/6/2024 | Approved | JOHN KIDWELL |
| Final | 11/18/2024 | Corrections Issued | JOHN KIDWELL |
| Green Building Final | 11/18/2024 | Approved | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 11/18/2024 | SGSOV Approved | JOHN KIDWELL |
| Smoke Detectors | 11/18/2024 | Approved | JOHN KIDWELL |
| Final | 1/28/2025 | OK to Issue CofO | JOHN KIDWELL |