12853 W ELKWOOD ST 91605
Certificate Information: 12853 W ELKWOOD ST 91605
- Application / Permit
- 24014-20000-00752
- Plan Check / Job No.
- B24VN02463
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT AND 38'-3" x 15'-1" ADDITION AND 17'-10" x 14'-2" ADDITION TO THE NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d). "COMPLY WITH DEPARTMENT ORDER effective date 10/27/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 2/5/2025
- Issuing Office
- Current Status
- Issued on 2/5/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/14/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/20/2024 | GIOVANNY CHAVEZ |
| Corrections Issued | 3/21/2024 | GIOVANNY CHAVEZ |
| Applicant returned to address corrections | 8/31/2024 | GIOVANNY CHAVEZ |
| Plan Check Approved | 9/17/2024 | GIOVANNY CHAVEZ |
| Issued | 2/5/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 4/8/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 5/6/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 5/6/2024 | BIAINA HARITUNIAN |
| Construction near power lines | Cleared | 8/6/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 8/6/2024 | RIDWAN HARDY |
| Low Impact Development (LID) | Cleared | 8/26/2024 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 8/28/2024 | BIAINA HARITUNIAN |
| Hold | Cleared | 4/15/2025 | ALEXIS SCHULTZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/15/2025 | No Access for Inspection | FELIPE PENICHE |
| PLUMBING-Rough | 4/16/2025 | Partial Approval | DAVID MATSON |
| Deputy Drilled-In Anchors | 4/24/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 4/28/2025 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 4/28/2025 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 8/21/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Rough | 8/21/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Floor/Roof Diaphrgm/Shear Wall | 8/21/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Green Building Rough | 8/21/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| HVAC-Rough | 8/21/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 8/21/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Floor/Roof Diaphrgm/Shear Wall | 9/11/2025 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2025 | Approved | OGANES TARAKHCHYAN |
| Rough-Elec/Plmb/HVAC | 12/2/2025 | Approved | OGANES TARAKHCHYAN |
| Gas Test | 12/19/2025 | Approved | LOUIS ESCOTO |
| Interior/Exterior Lathing | 12/19/2025 | Partial Approval | LOUIS ESCOTO |
| Insulation | 12/24/2025 | No Access for Inspection | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 1/5/2026 | Partial Approval | OGANES TARAKHCHYAN |
| Insulation | 1/7/2026 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 1/23/2026 | Approved | JOSH MEISTER |
| Green Building Rough | 1/23/2026 | Approved | JOSH MEISTER |
| Shower Pan | 1/27/2026 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 1/30/2026 | Approved | OGANES TARAKHCHYAN |
| Underground Mechanical | 5/11/2026 | Partial Approval | MATTHEW NELSON |