5652 N LEMP AVE 91601

Certificate Information: 5652 N LEMP AVE 91601

Application / Permit
24014-20000-00735
Plan Check / Job No.
B24VN02381
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN (N) ADDITION TO (E) SFD
Permit Issued
Issued on 8/14/2024
Issuing Office
Current Status
CofO Issued on 10/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/3/2024 APPLICANT
Assigned to Plan Check Engineer 3/6/2024 JOHNPAUL ISIP
Corrections Issued 3/6/2024 JOHNPAUL ISIP
Applicant returned to address corrections 5/2/2024 JOHNPAUL ISIP
Applicant returned to address corrections 5/9/2024 REZA HAGHIGHAT
Plan Check Approved 8/4/2024 REZA HAGHIGHAT
Issued 8/14/2024 APPLICANT
CofO in Progress 9/30/2025 JAVIER RAMOS JR
Permit Finaled 10/23/2025 RUBEN SALAS
CofO Issued 10/23/2025 RUBEN SALAS
Permit Finaled 10/23/2025 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/10/2024 CARLOS AGUILERA
Sewer availability Cleared 5/10/2024 CARLOS AGUILERA
Low Impact Development (LID) Cleared 7/24/2024 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 7/29/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22814 DOLOROSA ST      WOODLAND HILLS, CA 91367

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/21/2024 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 8/21/2024 Approved CHRISTOPHER ROJAS
Footing/Foundation/Slab 9/6/2024 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Rough 9/6/2024 Partial Approval CHRISTOPHER ROJAS
BUILDING-Rough-Frame 9/9/2024 Partial Approval CHRISTOPHER ROJAS
Green Building Rough 9/9/2024 Approved CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 9/25/2024 Partial Approval CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 10/29/2024 Approved CHRISTOPHER ROJAS
Underground Mechanical 12/12/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 12/26/2024 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 12/26/2024 Partial Inspection CHRISTOPHER ROJAS
HVAC-Rough 12/26/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 1/9/2025 Partial Approval CHRISTOPHER ROJAS
ELECTRICAL-Rough 1/9/2025 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 1/9/2025 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 1/14/2025 Approved MISAEL ESPARZA
ELECTRICAL-Rough 1/14/2025 Approved MISAEL ESPARZA
Insulation 1/14/2025 Approved MISAEL ESPARZA
Drywall Nailing 1/24/2025 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 1/24/2025 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 1/31/2025 Approved MICHAEL CORTEZ
Shower Pan 1/31/2025 Approved MICHAEL CORTEZ
ELECTRICAL-Final 9/18/2025 Approved JAVIER RAMOS JR
Final 9/18/2025 Corrections Issued JAVIER RAMOS JR
Green Building Final 9/18/2025 Approved JAVIER RAMOS JR
HVAC-Final 9/18/2025 Approved JAVIER RAMOS JR
PLUMBING-Final 9/18/2025 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 9/18/2025 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 9/18/2025 Approved JAVIER RAMOS JR
Final 9/30/2025 OK to Issue CofO JAVIER RAMOS JR
Footing/Foundation/Slab 9/30/2025 Approved JAVIER RAMOS JR