6430 N LONGRIDGE AVE 91401
Certificate Information: 6430 N LONGRIDGE AVE 91401
- Application / Permit
- 24014-20000-00725
- Plan Check / Job No.
- B24VN02357
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Major Remodel to existing 1-story Single Family Dwelling with (35'-4" x 21'-7" Irregular Shape) Addition on the south side and (48'-4" x 28'-9" Irregular Shape) Addition on the northeast side. NFPA 13D Fire Sprinklers Throughout.
- Permit Issued
- Issued on 3/13/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/22/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/29/2024 | VAHAN JIVALAGIAN |
| Corrections Issued | 3/3/2024 | VAHAN JIVALAGIAN |
| Quality Review Completed | 3/6/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 3/7/2024 | APPLICANT |
| Plan Check Approved | 3/13/2024 | VAHAN JIVALAGIAN |
| Issued | 3/13/2024 | APPLICANT |
| CofO in Progress | 7/26/2024 | OGANES TARAKHCHYAN |
| No Progress | 8/7/2024 | ROBERT GOLD |
| CofO in Progress | 8/7/2024 | ROBERT GOLD |
| CofO Issued | 8/15/2024 | DANIEL ORRANTE |
| Permit Finaled | 8/15/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/6/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 3/6/2024 | CARLOS AGUILERA |
| Low Impact Development (LID) | Cleared | 3/8/2024 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 3/9/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/22/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 3/22/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Underground Mechanical | 3/22/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 3/26/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 3/27/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Underground Mechanical | 3/27/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Gas Test | 4/1/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 4/1/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Underground Mechanical | 4/1/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Deputy Shotcrete | 4/3/2024 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Gas Test | 4/3/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Deputy Wood Construction | 4/22/2024 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/23/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 5/6/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 5/6/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Verify Sprinkler Sign Off | 5/6/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 5/8/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 5/8/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 5/8/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 5/8/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 5/9/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 5/9/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 5/9/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Shower Pan | 5/9/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 5/10/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 5/10/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 5/10/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 5/10/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 5/13/2024 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 5/14/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 5/14/2024 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 5/14/2024 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 5/16/2024 | Approved | JOHN COLEMAN |
| Sewer | 5/20/2024 | Approved | OGANES TARAKHCHYAN |
| Enclosure/Fence | 6/18/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 6/20/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Green Building Final | 6/20/2024 | Not Ready for Inspection | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 6/20/2024 | SGSOV Not Ready | RYAN SALAZAR |
| Smoke Detectors | 6/20/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Green Building Final | 7/2/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 7/2/2024 | SGSOV Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 7/2/2024 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 7/12/2024 | Approved | OGANES TARAKHCHYAN |
| Final | 7/25/2024 | OK to Issue CofO | OGANES TARAKHCHYAN |
| Green Building Final | 7/25/2024 | Approved | OGANES TARAKHCHYAN |