7164 S KNOWLTON PL 90045
Certificate Information: 7164 S KNOWLTON PL 90045
- Application / Permit
- 24014-20000-00715
- Plan Check / Job No.
- B24VN02304
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL, 18'-10" x 27'-0" IRREGULAR SHAPED ADDITION WITH 13'-4" x 28'-4" OPEN TRELLIS TO (E) SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 4/4/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/8/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/21/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/26/2024 | ARTIN ZARUKIAN |
| Corrections Issued | 2/26/2024 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 2/29/2024 | APPLICANT |
| Plan Check Approved | 3/26/2024 | GIOVANNY CHAVEZ |
| Issued | 4/4/2024 | APPLICANT |
| CofO in Progress | 7/3/2025 | DAVID FEILER |
| CofO Issued | 7/8/2025 | RICHARD STEINBACH |
| Permit Finaled | 7/8/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/5/2024 | CHARLES POWELL |
| Specific Plan | Cleared | 3/13/2024 | JOSHUA JONES |
| Eng Process Fee Ord 176,300 | Cleared | 3/15/2024 | DARIN LAM |
| Sewer availability | Cleared | 3/15/2024 | DARIN LAM |
| Roof/Waste drainage to street | Cleared | 3/19/2024 | DARIN LAM |
| GPI Written Notices | Cleared | 3/26/2024 | ARTIN ZARUKIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ebrahimi,, Amirhosin; Lic. No.: C92049 | 8619 RESEDA BLVD UNIT 304B NORTHRIDGE, CA 91324 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/1/2024 | Not Ready for Inspection | BOBBY KEY |
| Footing/Foundation/Slab | 5/1/2024 | Corrections Issued | BOBBY KEY |
| Footing/Foundation/Slab | 5/7/2024 | Partial Approval | BOBBY KEY |
| Special/Order Compliance | 5/7/2024 | Corrections Issued | BOBBY KEY |
| Deputy Steel/Welding | 5/16/2024 | Conditional Approval | BOBBY KEY |
| Footing/Foundation/Slab | 5/17/2024 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/31/2024 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 5/31/2024 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 6/4/2024 | Partial Approval | BOBBY KEY |
| Wood Frame | 6/4/2024 | Partial Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 7/24/2024 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2024 | Corrections Issued | BOBBY KEY |
| Special/Order Compliance | 7/24/2024 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 8/7/2024 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2024 | Approved | BOBBY KEY |
| HVAC-Rough | 8/7/2024 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 8/7/2024 | Corrections Issued | BOBBY KEY |
| HVAC-Rough | 8/13/2024 | Approved | BOBBY KEY |
| PLUMBING-Rough | 8/13/2024 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 8/22/2024 | Corrections Issued | DAVID FEILER |
| Shower Pan | 8/22/2024 | Corrections Issued | DAVID FEILER |
| BUILDING-Rough-Frame | 8/27/2024 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 8/27/2024 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 8/27/2024 | Approved | JESUS RODRIGUEZ |
| MERV13>=Rough | 8/27/2024 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 8/27/2024 | Approved | JESUS RODRIGUEZ |
| Insulation | 9/3/2024 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 9/30/2024 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 6/27/2025 | Approved | RUBEN RIVAS |
| Final | 6/27/2025 | Partial Approval | RUBEN RIVAS |
| Green Building Final | 6/27/2025 | Approved | RUBEN RIVAS |
| HVAC-Final | 6/27/2025 | Approved | RUBEN RIVAS |
| MERV13>=Final | 6/27/2025 | Approved | RUBEN RIVAS |
| PLUMBING-Final | 6/27/2025 | Approved | RUBEN RIVAS |
| SGSOV-Seismic Gas S/O Valve | 6/27/2025 | SGSOV Approved | RUBEN RIVAS |
| Smoke Detectors | 6/27/2025 | Approved | RUBEN RIVAS |
| Final | 7/3/2025 | OK to Issue CofO | DAVID FEILER |