12758 W KITTRIDGE ST 91606
Certificate Information: 12758 W KITTRIDGE ST 91606
- Application / Permit
- 24014-20000-00695
- Plan Check / Job No.
- B24VN02238
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL TO EXISTING 1-STORY SINGLE FAMILYW/ATTACHED GARAGE INCLUDING REMOVING ALL EXTERIOR/INTERIOR WALLS EXCEPT FOR 24'-1" EXTERIOR WALL AND BUILD NEW (42'-10"x48'-7"), 2778 SQFT SINGLE FAMILY DWELLING. W/ATTACHED COVERED PORCH (47 SQFT) W/ATTACHED 2-CAR GARAGE (341 SQFT) W/NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 3/7/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/24/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/20/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/22/2024 | PETER MOSESIAN |
| Corrections Issued | 2/24/2024 | PETER MOSESIAN |
| Quality Review Completed | 2/28/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 2/29/2024 | APPLICANT |
| Plan Check Approved | 3/7/2024 | PETER MOSESIAN |
| Issued | 3/7/2024 | APPLICANT |
| CofO in Progress | 12/17/2024 | OGANES TARAKHCHYAN |
| Permit Finaled | 12/24/2024 | RUBEN SALAS |
| CofO Issued | 12/24/2024 | RUBEN SALAS |
| Permit Finaled | 12/24/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/27/2024 | LEE GUILBEAUX |
| Sewer availability | Cleared | 2/27/2024 | LEE GUILBEAUX |
| Low Impact Development (LID) | Cleared | 2/28/2024 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 2/29/2024 | CARLOS RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yenjai,, Seree; Lic. No.: C73151 | 3249 SHADYLAWN DRIVE DUARTE, CA 91010 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/15/2024 | Approved | JOSE AVILA |
| Footing/Foundation/Slab | 3/29/2024 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 4/3/2024 | Partial Approval | JOSE AVILA |
| Deputy Steel/Welding | 4/9/2024 | Conditional Approval | JUAN VALENZUELA |
| Deputy Drilled-In Anchors | 4/10/2024 | Conditional Approval | JUAN VALENZUELA |
| Deputy Reinf. Concrete | 4/10/2024 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 4/10/2024 | Partial Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 4/29/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 4/29/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2024 | Partial Approval | JOSE AVILA |
| Footing/Foundation/Slab | 5/1/2024 | Approved | JOSE AVILA |
| Insulation | 5/3/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Insulation | 5/7/2024 | Partial Approval | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Reinforced Masonry Frame | 5/10/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Deputy Steel/Welding | 5/13/2024 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 6/11/2024 | Partial Approval | MISAEL ESPARZA |
| Deputy Wood Construction | 7/24/2024 | Conditional Approval | ROBERT GOLD |
| PLUMBING-Rough | 8/9/2024 | Approved | OGANES TARAKHCHYAN |
| Deputy Drilled-In Anchors | 8/12/2024 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2024 | Partial Approval | ARUTYUN MADATYAN |
| Wood Frame | 8/19/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2024 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 8/28/2024 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 9/3/2024 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 9/3/2024 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 9/9/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Shower Pan | 9/9/2024 | Approved | OGANES TARAKHCHYAN |
| Insulation | 9/11/2024 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 9/17/2024 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 9/17/2024 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 9/17/2024 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 12/6/2024 | Approved | OGANES TARAKHCHYAN |
| HVAC-Final | 12/6/2024 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 12/6/2024 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 12/11/2024 | Approved | OGANES TARAKHCHYAN |
| Service/Power Release | 12/11/2024 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 12/16/2024 | Approved | OGANES TARAKHCHYAN |
| Final | 12/16/2024 | OK to Issue CofO | OGANES TARAKHCHYAN |
| Green Building Final | 12/16/2024 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 12/16/2024 | SGSOV Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 12/16/2024 | Approved | OGANES TARAKHCHYAN |