12758 W KITTRIDGE ST 91606

Certificate Information: 12758 W KITTRIDGE ST 91606

Application / Permit
24014-20000-00695
Plan Check / Job No.
B24VN02238
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL TO EXISTING 1-STORY SINGLE FAMILYW/ATTACHED GARAGE INCLUDING REMOVING ALL EXTERIOR/INTERIOR WALLS EXCEPT FOR 24'-1" EXTERIOR WALL AND BUILD NEW (42'-10"x48'-7"), 2778 SQFT SINGLE FAMILY DWELLING. W/ATTACHED COVERED PORCH (47 SQFT) W/ATTACHED 2-CAR GARAGE (341 SQFT) W/NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 3/7/2024
Issuing Office
Valley
Current Status
CofO Issued on 12/24/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/20/2024 APPLICANT
Assigned to Plan Check Engineer 2/22/2024 PETER MOSESIAN
Corrections Issued 2/24/2024 PETER MOSESIAN
Quality Review Completed 2/28/2024 OMID HEDAYAT
Building Plans Picked Up 2/29/2024 APPLICANT
Plan Check Approved 3/7/2024 PETER MOSESIAN
Issued 3/7/2024 APPLICANT
CofO in Progress 12/17/2024 OGANES TARAKHCHYAN
Permit Finaled 12/24/2024 RUBEN SALAS
CofO Issued 12/24/2024 RUBEN SALAS
Permit Finaled 12/24/2024 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/27/2024 LEE GUILBEAUX
Sewer availability Cleared 2/27/2024 LEE GUILBEAUX
Low Impact Development (LID) Cleared 2/28/2024 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 2/29/2024 CARLOS RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/15/2024 Approved JOSE AVILA
Footing/Foundation/Slab 3/29/2024 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 4/3/2024 Partial Approval JOSE AVILA
Deputy Steel/Welding 4/9/2024 Conditional Approval JUAN VALENZUELA
Deputy Drilled-In Anchors 4/10/2024 Conditional Approval JUAN VALENZUELA
Deputy Reinf. Concrete 4/10/2024 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 4/10/2024 Partial Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 4/29/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 4/29/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 4/29/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 5/1/2024 Partial Approval JOSE AVILA
Footing/Foundation/Slab 5/1/2024 Approved JOSE AVILA
Insulation 5/3/2024 Not Ready for Inspection SALVADOR MARTINEZ
Insulation 5/7/2024 Partial Approval JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 5/10/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Reinforced Masonry Frame 5/10/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Deputy Steel/Welding 5/13/2024 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 6/11/2024 Partial Approval MISAEL ESPARZA
Deputy Wood Construction 7/24/2024 Conditional Approval ROBERT GOLD
PLUMBING-Rough 8/9/2024 Approved OGANES TARAKHCHYAN
Deputy Drilled-In Anchors 8/12/2024 Conditional Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 8/19/2024 Partial Approval ARUTYUN MADATYAN
Wood Frame 8/19/2024 Not Ready for Inspection ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 8/26/2024 Approved OGANES TARAKHCHYAN
ELECTRICAL-Rough 8/28/2024 Approved OGANES TARAKHCHYAN
HVAC-Rough 9/3/2024 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 9/3/2024 Partial Approval OGANES TARAKHCHYAN
BUILDING-Rough-Frame 9/9/2024 Partial Approval OGANES TARAKHCHYAN
Shower Pan 9/9/2024 Approved OGANES TARAKHCHYAN
Insulation 9/11/2024 Approved OGANES TARAKHCHYAN
Drywall Nailing 9/17/2024 Approved OGANES TARAKHCHYAN
Green Building Rough 9/17/2024 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 9/17/2024 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 12/6/2024 Approved OGANES TARAKHCHYAN
HVAC-Final 12/6/2024 Approved OGANES TARAKHCHYAN
PLUMBING-Final 12/6/2024 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 12/11/2024 Approved OGANES TARAKHCHYAN
Service/Power Release 12/11/2024 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 12/16/2024 Approved OGANES TARAKHCHYAN
Final 12/16/2024 OK to Issue CofO OGANES TARAKHCHYAN
Green Building Final 12/16/2024 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 12/16/2024 SGSOV Approved OGANES TARAKHCHYAN
Smoke Detectors 12/16/2024 Approved OGANES TARAKHCHYAN