1111 1/2 W 48TH ST 90037
Certificate Information: 1111 1/2 W 48TH ST 90037
- Application / Permit
- 24014-20000-00686
- Plan Check / Job No.
- B24VN02207
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan: Detached 1-Story Garage Conversion to ADU w/Addition per LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 3/26/2024
- Issuing Office
- Current Status
- CofO Issued on 4/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/22/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/26/2024 | DAVID CASTILLO |
| Corrections Issued | 2/27/2024 | DAVID CASTILLO |
| Applicant returned to address corrections | 3/12/2024 | DAVID CASTILLO |
| Plan Check Approved | 3/22/2024 | DAVID CASTILLO |
| Issued | 3/26/2024 | APPLICANT |
| CofO in Progress | 4/15/2025 | BARRY HACHE |
| Permit Finaled | 4/19/2025 | DEROLD HAUFF |
| CofO Issued | 4/19/2025 | DEROLD HAUFF |
| Permit Finaled | 4/19/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/29/2024 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 2/29/2024 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 3/4/2024 | WALLIE JONG |
| Sewer availability | Cleared | 3/4/2024 | WALLIE JONG |
| Community Plan Implem. Overlay | Cleared | 3/14/2024 | MANERI ROMAN |
Contact Information
| Contractor | Next Generation Builders; Lic. No.: 1069728-B | , |
| Contractor | Polymath Development Group Inc; Lic. No.: 1069728-B | , |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVE SUITE 201 LONG BEACH, CA 90813 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/9/2024 | Partial Approval | CRAIG DAVIS |
| PLUMBING-Rough | 5/9/2024 | Corrections Issued | CRAIG DAVIS |
| Footing/Foundation/Slab | 5/13/2024 | Not Ready for Inspection | CRAIG DAVIS |
| Sewer | 5/13/2024 | Approved | CRAIG DAVIS |
| Excavation/Setback/Form/Re-Bar | 5/15/2024 | Partial Inspection | ANTHONY EGSON |
| Sewer | 5/15/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Sewer | 5/22/2024 | Not Ready for Inspection | CRAIG DAVIS |
| Underground Mechanical | 5/22/2024 | Corrections Issued | CRAIG DAVIS |
| Gas Test | 5/24/2024 | Not Ready for Inspection | CRAIG DAVIS |
| Sewer | 5/24/2024 | Corrections Issued | CRAIG DAVIS |
| Gas Test | 6/3/2024 | Partial Approval | CRAIG DAVIS |
| PLUMBING-Rough | 6/3/2024 | Partial Approval | CRAIG DAVIS |
| Sewer | 6/3/2024 | Not Ready for Inspection | CRAIG DAVIS |
| Sewer | 6/5/2024 | Not Ready for Inspection | CRAIG DAVIS |
| Sewer | 6/20/2024 | Partial Inspection | CRAIG DAVIS |
| Sewer | 6/25/2024 | Corrections Issued | CRAIG DAVIS |
| Footing/Foundation/Slab | 10/18/2024 | Corrections Issued | BRENDAN MORELLI |
| Excavation/Setback/Form/Re-Bar | 12/12/2024 | Approved | CRAIG DAVIS |
| ELECTRICAL-Final | 4/4/2025 | Approved | BARRY HACHE |
| BUILDING-Rough-Frame | 4/14/2025 | Approved | BARRY HACHE |
| Final | 4/14/2025 | OK to Issue CofO | BARRY HACHE |
| Footing/Foundation/Slab | 4/14/2025 | Approved | BARRY HACHE |
| Green Building Final | 4/14/2025 | Approved | BARRY HACHE |
| Green Building Rough | 4/14/2025 | Approved | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 4/14/2025 | SGSOV Approved | BARRY HACHE |
| Smoke Detectors | 4/14/2025 | Approved | BARRY HACHE |