3434 N GRIFFITH PARK BLVD 90027
Certificate Information: 3434 N GRIFFITH PARK BLVD 90027
- Application / Permit
- 24014-20000-00683
- Plan Check / Job No.
- B24VN02206
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT ATTIC SPACE TO 65 SF BATHROOM ADDITION. WORK PER ENGINEERED DESIGN.
- Permit Issued
- Issued on 3/20/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/20/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/23/2024 | JESSE ARELLANO |
| Corrections Issued | 2/24/2024 | JESSE ARELLANO |
| Building Plans Picked Up | 3/4/2024 | APPLICANT |
| Applicant returned to address corrections | 3/19/2024 | OMAR GARNICA |
| Plan Check Approved | 3/20/2024 | ISIS ARGUETA |
| Issued | 3/20/2024 | APPLICANT |
| CofO in Progress | 1/16/2025 | JEFFREY MEAD |
| Permit Finaled | 1/26/2025 | DEROLD HAUFF |
| CofO Issued | 1/26/2025 | DEROLD HAUFF |
| Permit Finaled | 1/26/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mniarji,, Majd Sameer; Lic. No.: C93049 | 7812 VASSAR AVENUE CANOGA PARK, CA 91304 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 11/18/2024 | Approved | BRENDAN MORELLI |
| HVAC-Rough | 11/18/2024 | Approved | BRENDAN MORELLI |
| PLUMBING-Rough | 11/18/2024 | Approved | BRENDAN MORELLI |
| Wood Frame | 11/18/2024 | Approved | BRENDAN MORELLI |
| Insulation | 11/20/2024 | Approved | ENRIQUE MIRELES |
| Shower Pan | 11/20/2024 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 11/25/2024 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 12/24/2024 | Approved | ENRIQUE MIRELES |
| Final | 12/24/2024 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 12/24/2024 | Approved | ENRIQUE MIRELES |
| Green Building Final | 12/24/2024 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 12/24/2024 | Approved | ENRIQUE MIRELES |
| Smoke Detectors | 12/24/2024 | Approved | ENRIQUE MIRELES |
| Final | 1/15/2025 | OK to Issue CofO | JEFFREY MEAD |