6629 N RANCHITO AVE 91405

Certificate Information: 6629 N RANCHITO AVE 91405

Application / Permit
24014-20000-00672
Plan Check / Job No.
B24VN02180
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) DETACHED 37'-4" X 33'-10" ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 4/2/2024
Issuing Office
Current Status
CofO Issued on 1/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/20/2024 APPLICANT
Assigned to Plan Check Engineer 2/23/2024 ALEC MOUSAKHANIAN
Corrections Issued 2/24/2024 ALEC MOUSAKHANIAN
Plan Check Approved 4/2/2024 ALEC MOUSAKHANIAN
Issued 4/2/2024 APPLICANT
CofO in Progress 12/11/2024 RYAN SALAZAR
Permit Finaled 1/7/2025 RUBEN SALAS
CofO Issued 1/7/2025 RUBEN SALAS
Permit Finaled 1/7/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/14/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 3/14/2024 BIAINA HARITUNIAN
Sewer availability Cleared 3/15/2024 BIAINA HARITUNIAN
Low Impact Development (LID) Cleared 3/29/2024 PATRICK LOPEZ
Roof/Waste drainage to street Cleared 3/29/2024 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/8/2024 Not Ready for Inspection MATTHEW NELSON
Excavation/Setback/Form/Re-Bar 6/11/2024 Corrections Issued RYAN SALAZAR
PLUMBING-Rough 6/11/2024 Not Ready for Inspection RYAN SALAZAR
PLUMBING-Rough 6/17/2024 Partial Approval RYAN SALAZAR
Footing/Foundation/Slab 8/14/2024 Approved RYAN SALAZAR
Deputy Drilled-In Anchors 9/4/2024 Approved RYAN SALAZAR
Deputy Wood Construction 9/4/2024 Approved RYAN SALAZAR
ELECTRICAL-Rough 9/4/2024 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 9/4/2024 Approved RYAN SALAZAR
HVAC-Rough 9/4/2024 Approved RYAN SALAZAR
PLUMBING-Rough 9/4/2024 Approved RYAN SALAZAR
Gas Test 9/9/2024 Approved RYAN SALAZAR
Insulation 9/9/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 9/9/2024 Approved RYAN SALAZAR
Shower Pan 9/9/2024 Approved RYAN SALAZAR
Drywall Nailing 9/12/2024 Approved RYAN SALAZAR
ELECTRICAL-Final 11/14/2024 Approved RYAN SALAZAR
Final 11/14/2024 Corrections Issued RYAN SALAZAR
Gas Test 11/14/2024 Approved RYAN SALAZAR
HVAC-Final 11/14/2024 Approved RYAN SALAZAR
PLUMBING-Final 11/14/2024 Corrections Issued RYAN SALAZAR
Smoke Detectors 11/14/2024 Approved RYAN SALAZAR
BUILDING-Rough-Frame 12/10/2024 Approved RYAN SALAZAR
Final 12/10/2024 OK to Issue CofO RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 12/10/2024 SGSOV Approved RYAN SALAZAR
Service/Power Release 12/10/2024 Approved RYAN SALAZAR