3104 S KELTON AVE 90034
Certificate Information: 3104 S KELTON AVE 90034
- Application / Permit
- 24014-20000-00638
- Plan Check / Job No.
- B24VN02031
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition and Major Remodel to existing 1-story Single Family Dwelling, 68 linear feet of exterior wall and foundation to remain on front and West side portion of Lot. Rebuilt as 2-story (64' 6" x 40' Irregular Shaped) Single Family Dwelling, attached garage and attached Trellis in the back. NFPA 13D Fire Sprinklers Throughout. All work done per engineer.
- Permit Issued
- Issued on 9/11/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/15/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/22/2024 | NAREG ATARIAN |
| Corrections Issued | 2/25/2024 | NAREG ATARIAN |
| Quality Review Completed | 2/27/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 2/29/2024 | APPLICANT |
| Plan Check Approved | 9/9/2024 | NAREG ATARIAN |
| Issued | 9/11/2024 | APPLICANT |
| CofO in Progress | 11/24/2025 | KIRK SANDERS |
| Permit Finaled | 11/29/2025 | RICHARD STEINBACH |
| CofO Issued | 11/29/2025 | RICHARD STEINBACH |
| Permit Finaled | 11/29/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 7/18/2024 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 7/22/2024 | DIANA RENTERIA |
| Eng Process Fee Ord 176,300 | Cleared | 7/23/2024 | KIMBERLY HERNANDEZ |
| Sewer availability | Cleared | 7/23/2024 | KIMBERLY HERNANDEZ |
| Specific Plan | Cleared | 8/5/2024 | RICHARD WOO |
| GPI Written Notices | Cleared | 9/9/2024 | MATTHEW JENKINS |
| Grading Pre-Inspection | Cleared | 9/9/2024 | MATTHEW JENKINS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Carrillo,, Jesus Eduardo; Lic. No.: C77737 | 8207 BROOKGREEN RD DOWNEY, CA 90240 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/25/2024 | Corrections Issued | BOBBY KEY |
| Underground Mechanical | 11/25/2024 | Partial Approval | BOBBY KEY |
| Excavation/Setback/Form/Re-Bar | 12/9/2024 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 1/7/2025 | Conditional Approval | DANIEL VERA |
| Deputy Wood Construction | 1/27/2025 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 1/28/2025 | Partial Approval | EVAN COOPER |
| HVAC-Rough | 2/27/2025 | Approved | EVAN COOPER |
| PLUMBING-Rough | 2/27/2025 | Approved | EVAN COOPER |
| ELECTRICAL-Rough | 3/10/2025 | Approved | WILBER ROSALES |
| Special/Order Compliance | 3/10/2025 | Partial Inspection | BOBBY KEY |
| BUILDING-Rough-Frame | 3/20/2025 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 3/20/2025 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 3/20/2025 | Partial Approval | ARAM AVEDISIAN |
| Insulation | 3/27/2025 | Approved | ARAM AVEDISIAN |
| Shower Pan | 3/27/2025 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 4/2/2025 | Approved | JAYLIN GRAVITTE |
| Drywall Nailing | 4/7/2025 | Approved | BOBBY KEY |
| Sewer | 6/10/2025 | Approved | ARAM AVEDISIAN |
| Underground Mechanical | 6/10/2025 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Final | 9/30/2025 | Approved | DANIEL VERA |
| Final | 9/30/2025 | Not Ready for Inspection | DANIEL VERA |
| Footing/Foundation/Slab | 9/30/2025 | Approved | DANIEL VERA |
| Gas Test | 9/30/2025 | Not Ready for Inspection | DANIEL VERA |
| Green Building Final | 9/30/2025 | Approved | DANIEL VERA |
| HVAC-Final | 9/30/2025 | Approved | DANIEL VERA |
| PLUMBING-Final | 9/30/2025 | Not Ready for Inspection | DANIEL VERA |
| SGSOV-Seismic Gas S/O Valve | 9/30/2025 | SGSOV Not Ready | DANIEL VERA |
| Service/Power Release | 9/30/2025 | Not Ready for Inspection | DANIEL VERA |
| Smoke Detectors | 9/30/2025 | Approved | DANIEL VERA |
| Gas Test | 10/2/2025 | Approved | MICHAEL ALLEN |
| PLUMBING-Final | 10/2/2025 | Approved | MICHAEL ALLEN |
| SGSOV-Seismic Gas S/O Valve | 10/2/2025 | SGSOV Approved | MICHAEL ALLEN |
| Verify Sprinkler Sign Off | 10/2/2025 | Approved | MICHAEL ALLEN |
| Final | 11/21/2025 | OK to Issue CofO | KIRK SANDERS |
| Service/Power Release | 11/21/2025 | Approved | KIRK SANDERS |