19550 W LANARK ST 91335

Certificate Information: 19550 W LANARK ST 91335

Application / Permit
24014-20000-00629
Plan Check / Job No.
B24VN01988
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition to Ex. SFD for three new bathrooms, new laundry and to expand (e) bedrooms/kitchen. Convert den to new bedroom. Remove existing 10'-6" x 30' att. patio cover. Automatic Fire Sprinkler System Required.
Permit Issued
Issued on 4/4/2024
Issuing Office
Valley
Current Status
CofO Issued on 5/27/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/14/2024 APPLICANT
Assigned to Plan Check Engineer 2/21/2024 JESSE ARELLANO
Corrections Issued 2/22/2024 JESSE ARELLANO
Building Plans Picked Up 2/26/2024 APPLICANT
Applicant returned to address corrections 4/2/2024 ANGELICA DAVE
Plan Check Approved 4/4/2024 ROSENDO MEDINA
Issued 4/4/2024 APPLICANT
CofO in Progress 4/17/2026 ARUTYUN MADATYAN
Permit Finaled 5/27/2026 JOHN JANSON
CofO Issued 5/27/2026 JOHN JANSON
Permit Finaled 5/27/2026 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/4/2024 BRYAN GODINEZ
Private sewage disp. approval Cleared 3/7/2024 MICHAEL TEMPLE
Low Impact Development (LID) Cleared 4/1/2024 TOMMY YIN
Roof/Waste drainage to street Cleared 4/2/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 4/2/2024 LEE GUILBEAUX

Contact Information

Contractor California Green Remodeling Inc; Lic. No.: 1100046-B 19550 LANARK ST      RESEDA, CA 91335
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/26/2024 Approved JEFFREY BULL
Deputy Drilled-In Anchors 7/12/2024 Approved JEFFREY BULL
Deputy Wood Construction 7/12/2024 Approved JEFFREY BULL
ELECTRICAL-Rough 8/21/2024 Approved JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 8/21/2024 Approved JEFFREY BULL
PLUMBING-Rough 8/21/2024 Approved JEFFREY BULL
Insulation 9/17/2024 Approved JEFFREY BULL
Interior/Exterior Lathing 9/17/2024 Approved JEFFREY BULL
Drywall Nailing 9/27/2024 Approved JEFFREY BULL
BUILDING-Rough-Frame 11/6/2024 Approved ARUTYUN MADATYAN
Final 11/6/2024 Not Ready for Inspection ARUTYUN MADATYAN
Green Building Final 11/6/2024 Not Ready for Inspection ARUTYUN MADATYAN
Green Building Rough 11/6/2024 Approved ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 11/6/2024 SGSOV Not Ready ARUTYUN MADATYAN
Smoke Detectors 11/6/2024 Not Ready for Inspection ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 12/26/2024 SGSOV Not Ready ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 1/8/2025 SGSOV Not Ready ARUTYUN MADATYAN
Final 1/15/2025 Corrections Issued ARUTYUN MADATYAN
Green Building Final 1/15/2025 Approved ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 1/15/2025 SGSOV Approved ARUTYUN MADATYAN
Smoke Detectors 1/15/2025 Approved ARUTYUN MADATYAN
Special/Order Compliance 1/15/2025 Partial Inspection JUAN ALVARADO
Special/Order Compliance 5/14/2025 Partial Inspection JUAN ALVARADO
ELECTRICAL-Final 4/16/2026 Approved ARUTYUN MADATYAN
Final 4/16/2026 OK to Issue CofO ARUTYUN MADATYAN
HVAC-Final 4/16/2026 Approved ARUTYUN MADATYAN
PLUMBING-Final 4/16/2026 Approved ARUTYUN MADATYAN
Service/Power Release 5/5/2026 Approved ARUTYUN MADATYAN