14012 W CANTLAY ST 91405

Certificate Information: 14012 W CANTLAY ST 91405

Application / Permit
24014-20000-00589
Plan Check / Job No.
B24VN01821
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN. 221 SF ADDITION TO EXISTING DWELLING. WORK PER ENGR.
Permit Issued
Issued on 2/25/2024
Issuing Office
Current Status
CofO Issued on 11/2/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/13/2024 APPLICANT
Assigned to Plan Check Engineer 2/13/2024 NEHEMIAS RAMOS
Corrections Issued 2/13/2024 NEHEMIAS RAMOS
Plan Check Approved 2/23/2024 NEHEMIAS RAMOS
Issued 2/25/2024 APPLICANT
CofO in Progress 10/24/2024 VINCENT HANLEY
CofO Issued 11/2/2024 DANIEL ORRANTE
Permit Finaled 11/2/2024 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/14/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 2/14/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Grigoryan,, Souren; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/16/2024 Conditional Approval DAVID MATSON
Excavation/Setback/Form/Re-Bar 4/16/2024 Approved GREGG CUMMINGS
Footing/Foundation/Slab 4/16/2024 Approved GREGG CUMMINGS
Deputy Reinf. Concrete 4/17/2024 Conditional Approval DAVID MATSON
BUILDING-Rough-Frame 4/25/2024 Partial Approval WILLIAM WREN
PLUMBING-Rough 4/25/2024 Partial Approval WILLIAM WREN
Insulation 4/29/2024 Partial Approval KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 5/6/2024 Partial Approval KIRK SANDERS
Deputy Wood Construction 5/22/2024 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 6/10/2024 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 6/10/2024 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 6/10/2024 Approved VINCENT HANLEY
Green Building Rough 6/10/2024 Not Ready for Inspection VINCENT HANLEY
HVAC-Rough 6/10/2024 Approved VINCENT HANLEY
PLUMBING-Rough 6/10/2024 Approved VINCENT HANLEY
BUILDING-Rough-Frame 7/22/2024 Approved VINCENT HANLEY
Green Building Rough 7/22/2024 Approved VINCENT HANLEY
Insulation 7/22/2024 Approved VINCENT HANLEY
Interior/Exterior Lathing 7/22/2024 Partial Approval VINCENT HANLEY
Shower Pan 7/22/2024 Approved VINCENT HANLEY
Drywall Nailing 7/30/2024 Approved JOSE AVILA
ELECTRICAL-Final 9/6/2024 Not Ready for Inspection VINCENT HANLEY
HVAC-Final 9/6/2024 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Final 9/6/2024 Not Ready for Inspection VINCENT HANLEY
Service/Power Release 9/6/2024 Approved VINCENT HANLEY
ELECTRICAL-Final 10/23/2024 Approved VINCENT HANLEY
Final 10/23/2024 OK to Issue CofO VINCENT HANLEY
Green Building Final 10/23/2024 Approved VINCENT HANLEY
HVAC-Final 10/23/2024 Approved VINCENT HANLEY
PLUMBING-Final 10/23/2024 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 10/23/2024 SGSOV Approved VINCENT HANLEY
Smoke Detectors 10/23/2024 Approved VINCENT HANLEY