6220 N BLUCHER AVE 91411
Certificate Information: 6220 N BLUCHER AVE 91411
- Application / Permit
- 24014-20000-00574
- Plan Check / Job No.
- B24VN01789
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO SFD
- Permit Issued
- Issued on 11/5/2024
- Issuing Office
- Current Status
- CofO Issued on 6/5/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/12/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/14/2024 | SERGIO MUNIZ |
| Corrections Issued | 2/15/2024 | SERGIO MUNIZ |
| Applicant returned to address corrections | 10/16/2024 | SERGIO MUNIZ |
| Applicant returned to address corrections | 10/31/2024 | SERGIO MUNIZ |
| Plan Check Approved | 11/5/2024 | SERGIO MUNIZ |
| Issued | 11/5/2024 | APPLICANT |
| CofO in Progress | 6/2/2025 | RYAN SALAZAR |
| Permit Finaled | 6/5/2025 | RUBEN SALAS |
| CofO Issued | 6/5/2025 | RUBEN SALAS |
| Permit Finaled | 6/5/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/22/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 4/22/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 4/24/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 4/24/2024 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 8/4/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yiu,, Siu; Lic. No.: S5801 | PO BOX 1752 TEMPLE CITY, CA 91780 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/18/2024 | Conditional Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 12/20/2024 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 1/3/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/6/2025 | Partial Approval | RYAN SALAZAR |
| PLUMBING-Rough | 1/6/2025 | Partial Approval | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 1/8/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Deputy Drilled-In Anchors | 1/29/2025 | Conditional Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 1/30/2025 | Partial Approval | MATTHEW NELSON |
| MERV13>=Rough | 1/30/2025 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 2/13/2025 | Corrections Issued | JACK KARGODORIAN |
| PLUMBING-Rough | 2/13/2025 | Approved | JACK KARGODORIAN |
| Wood Frame | 2/13/2025 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 2/19/2025 | Partial Approval | RYAN SALAZAR |
| Insulation | 2/24/2025 | Corrections Issued | LOUIS ESCOTO |
| Interior/Exterior Lathing | 2/24/2025 | Approved | LOUIS ESCOTO |
| Drywall Nailing | 3/6/2025 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 3/6/2025 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 4/16/2025 | Approved | RYAN SALAZAR |
| Final | 4/16/2025 | Corrections Issued | RYAN SALAZAR |
| MERV13>=Final | 4/16/2025 | Approved | RYAN SALAZAR |
| MERV13>=Rough | 4/16/2025 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 4/16/2025 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 4/16/2025 | Approved | RYAN SALAZAR |
| Final | 5/27/2025 | OK to Issue CofO | RYAN SALAZAR |