6817 W 88TH ST 90045
Certificate Information: 6817 W 88TH ST 90045
- Application / Permit
- 24014-20000-00571
- Plan Check / Job No.
- B24VN01776
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 11'4"X20'8" BEDROOM ADDITION TO EXISTING SFD
- Permit Issued
- Issued on 5/23/2024
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 10/25/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/12/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/16/2024 | HAYATO TSUCHIYA |
| Corrections Issued | 2/17/2024 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 2/22/2024 | APPLICANT |
| Plan Check Approved | 5/23/2024 | GURUNATH NESARAJAH |
| Issued | 5/23/2024 | APPLICANT |
| CofO in Progress | 10/24/2024 | BOBBY KEY |
| Permit Finaled | 10/25/2024 | RICHARD STEINBACH |
| CofO Issued | 10/25/2024 | RICHARD STEINBACH |
| Permit Finaled | 10/25/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 3/4/2024 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 3/5/2024 | DARIN LAM |
| Specific Plan | Cleared | 3/7/2024 | JOSHUA JONES |
Contact Information
| Architect | Miller,, Michael; Lic. No.: C26956 | 12756 MITCHELL AVE LOS ANGELES, CA 90066 |
| Contractor | Bela Development; Lic. No.: 1038287-B | 1023 1/2 ABBOT KINNEY BLVD VENICE, CA 90291 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/24/2024 | Corrections Issued | BOBBY KEY |
| Deputy Drilled-In Anchors | 7/26/2024 | Conditional Approval | BOBBY KEY |
| Deputy Drilled-In Anchors | 8/1/2024 | Conditional Approval | BOBBY KEY |
| Footing/Foundation/Slab | 8/1/2024 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 8/5/2024 | Approved | BOBBY KEY |
| Wood Frame | 8/8/2024 | Partial Approval | RICHARD STEINBACH |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2024 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Rough | 8/23/2024 | Approved | BOBBY KEY |
| Deputy Wood Construction | 9/9/2024 | Conditional Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/11/2024 | Approved | BOBBY KEY |
| HVAC-Rough | 9/11/2024 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 9/17/2024 | Approved | BOBBY KEY |
| Green Building Rough | 9/17/2024 | Approved | BOBBY KEY |
| Insulation | 9/17/2024 | Corrections Issued | BOBBY KEY |
| Interior/Exterior Lathing | 9/17/2024 | Corrections Issued | BOBBY KEY |
| Insulation | 9/19/2024 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 9/19/2024 | Approved | BOBBY KEY |
| Drywall Nailing | 9/24/2024 | Approved | TEMISTOCLES CAAL |
| Special/Order Compliance | 9/24/2024 | Partial Inspection | HERBERT GIRON |
| ELECTRICAL-Final | 10/21/2024 | Approved | BOBBY KEY |
| Final | 10/21/2024 | Corrections Issued | BOBBY KEY |
| Green Building Final | 10/21/2024 | Approved | BOBBY KEY |
| HVAC-Final | 10/21/2024 | Approved | BOBBY KEY |
| PLUMBING-Final | 10/21/2024 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 10/21/2024 | SGSOV Not Ready | BOBBY KEY |
| Smoke Detectors | 10/21/2024 | Approved | BOBBY KEY |
| Final | 10/24/2024 | OK to Issue CofO | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 10/24/2024 | SGSOV Approved | BOBBY KEY |