13810 W COLLINS ST 91401

Certificate Information: 13810 W COLLINS ST 91401

Application / Permit
24014-20000-00553
Plan Check / Job No.
B24VN01727
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN CONVERSION OF EXISTING ACCESSORY STRUCTURE WITH ADDITION TO ADU PER ORDINANCE
Permit Issued
Issued on 4/16/2024
Issuing Office
Current Status
CofO Issued on 7/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/12/2024 APPLICANT
Assigned to Plan Check Engineer 2/15/2024 MINA HABILI
Corrections Issued 2/16/2024 MINA HABILI
Applicant returned to address corrections 3/27/2024 JOSEPH RAFOLS
Applicant returned to address corrections 4/2/2024 MINA HABILI
Applicant returned to address corrections 4/6/2024 MINA HABILI
Applicant returned to address corrections 4/10/2024 MINA HABILI
Plan Check Approved 4/15/2024 JOSEPH RAFOLS
Issued 4/16/2024 APPLICANT
CofO in Progress 7/17/2025 RYAN SALAZAR
Permit Finaled 7/29/2025 RUBEN SALAS
CofO Issued 7/29/2025 RUBEN SALAS
Permit Finaled 7/29/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/22/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 3/22/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 3/26/2024 BIAINA HARITUNIAN
Sewer availability Cleared 3/26/2024 BIAINA HARITUNIAN

Contact Information

Architect , ; Lic. No.: C33608       ,
Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/13/2024 Approved DAVID ANDERSON
PLUMBING-Rough 6/24/2024 Partial Approval DAVID ANDERSON
Special/Order Compliance 6/24/2024 Corrections Issued DAVID ANDERSON
Footing/Foundation/Slab 7/22/2024 Corrections Issued RYAN SALAZAR
Excavation/Setback/Form/Re-Bar 9/18/2024 Approved SALVADOR MARTINEZ
Footing/Foundation/Slab 9/18/2024 Approved SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 12/12/2024 Partial Approval RYAN SALAZAR
Underground Mechanical 12/12/2024 Approved RYAN SALAZAR
BUILDING-Rough-Frame 1/6/2025 Partial Approval RYAN SALAZAR
ELECTRICAL-Rough 1/6/2025 Approved RYAN SALAZAR
Gas Test 1/6/2025 Approved RYAN SALAZAR
Green Building Rough 1/6/2025 Approved RYAN SALAZAR
PLUMBING-Rough 1/6/2025 Approved RYAN SALAZAR
Wood Frame 1/6/2025 Approved RYAN SALAZAR
Insulation 1/24/2025 Approved RYAN SALAZAR
Interior/Exterior Lathing 1/24/2025 Partial Approval RYAN SALAZAR
Sewer 1/24/2025 Approved RYAN SALAZAR
Drywall Nailing 1/29/2025 Approved RYAN SALAZAR
Shower Pan 1/29/2025 Approved RYAN SALAZAR
BUILDING-Rough-Frame 7/18/2025 Approved RYAN SALAZAR
Final 7/18/2025 OK to Issue CofO RYAN SALAZAR
Green Building Final 7/18/2025 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 7/18/2025 SGSOV Approved RYAN SALAZAR
Smoke Detectors 7/18/2025 Approved RYAN SALAZAR