19006 W CALVERT ST 91335
Certificate Information: 19006 W CALVERT ST 91335
- Application / Permit
- 24014-20000-00552
- Plan Check / Job No.
- B24VN01725
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN Convert (E) detached garage and (E) 186 SF recroom into an Accessory Dwelling Unit per Ordinance with trellis addition. "COMPLY WITH DEPARTMENT ORDER effective date 12/11/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 8/12/2024
- Issuing Office
- Current Status
- CofO Issued on 12/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/12/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/22/2024 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 2/26/2024 | FARSHAD ALIMOHAMADI |
| Quality Review Completed | 3/8/2024 | CAROLYNN NEPOMUCENO |
| Applicant returned to address corrections | 4/5/2024 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 7/1/2024 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 7/2/2024 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 8/2/2024 | FARSHAD ALIMOHAMADI |
| Issued | 8/12/2024 | APPLICANT |
| CofO in Progress | 9/2/2025 | KIM BEAUCHAMP |
| Permit Finaled | 12/23/2025 | DAVID JAMES |
| CofO Issued | 12/23/2025 | DAVID JAMES |
| Permit Finaled | 12/23/2025 | DAVID JAMES |
Permit Application Clearance Information
| ZI | Cleared | 2/27/2024 | NATHAN ROMINE |
| Address approval | Cleared | 3/2/2024 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/26/2024 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 3/26/2024 | CARLOS RAMIREZ |
| Roof/Waste drainage to street | Cleared | 4/15/2024 | CARLOS RAMIREZ |
| Construction near power lines | Cleared | 6/21/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIO CUEVAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/4/2024 | Approved | KIM BEAUCHAMP |
| Deputy Drilled-In Anchors | 9/17/2024 | Approved | ARA SINANIAN |
| Deputy Drilled-In Anchors | 10/16/2024 | Approved | KIM BEAUCHAMP |
| Footing/Foundation/Slab | 10/16/2024 | Approved | KIM BEAUCHAMP |
| Sewer | 11/5/2024 | Corrections Issued | KIM BEAUCHAMP |
| Floor/Roof Diaphrgm/Shear Wall | 11/19/2024 | Approved | KIM BEAUCHAMP |
| Interior/Exterior Lathing | 11/22/2024 | Partial Approval | KIM BEAUCHAMP |
| ELECTRICAL-Rough | 11/25/2024 | Approved | KIM BEAUCHAMP |
| Gas Test | 11/25/2024 | Partial Approval | KIM BEAUCHAMP |
| Insulation | 11/26/2024 | Approved | KIM BEAUCHAMP |
| Drywall Nailing | 12/9/2024 | Approved | KIM BEAUCHAMP |
| Rough-Elec/Plmb/HVAC | 12/9/2024 | Approved | KIM BEAUCHAMP |
| Interior/Exterior Lathing | 12/26/2024 | Approved | KIM BEAUCHAMP |
| Shower Pan | 12/26/2024 | Approved | KIM BEAUCHAMP |
| BUILDING-Rough-Frame | 5/21/2025 | Approved | KIM BEAUCHAMP |
| Final | 5/21/2025 | Corrections Issued | KIM BEAUCHAMP |
| Green Building Final | 5/21/2025 | Approved | KIM BEAUCHAMP |
| Green Building Rough | 5/21/2025 | Approved | KIM BEAUCHAMP |
| SGSOV-Seismic Gas S/O Valve | 5/21/2025 | SGSOV Approved | KIM BEAUCHAMP |
| Smoke Detectors | 5/21/2025 | Approved | KIM BEAUCHAMP |
| Final | 8/29/2025 | OK to Issue CofO | KIM BEAUCHAMP |