13585 W DYER ST 91342
Certificate Information: 13585 W DYER ST 91342
- Application / Permit
- 24014-20000-00540
- Plan Check / Job No.
- B24VN01699
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan ADDITION TO FRONT OF (E) SFD
- Permit Issued
- Issued on 1/15/2025
- Issuing Office
- Current Status
- CofO Issued on 9/24/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/8/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2024 | NEHEMIAS RAMOS |
| Corrections Issued | 2/14/2024 | NEHEMIAS RAMOS |
| Applicant returned to address corrections | 3/11/2024 | NEHEMIAS RAMOS |
| Plan Check Approved | 3/18/2024 | NEHEMIAS RAMOS |
| Issued | 1/15/2025 | APPLICANT |
| CofO in Progress | 9/22/2025 | KEVIN BERBERYAN |
| Permit Finaled | 9/24/2025 | RUBEN SALAS |
| CofO Issued | 9/24/2025 | RUBEN SALAS |
| Permit Finaled | 9/24/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 3/2/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 3/2/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 3/4/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Terrio,, Greyson Franklin; Lic. No.: C87383 | 22647 VENTURA BLVD 362 WOODLAND HILLS, CA 91364 |
| Engineer | Terrio,, Greyson Franklin; Lic. No.: NA87383 | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/12/2025 | Partial Approval | KEVIN BERBERYAN |
| Deputy Drilled-In Anchors | 6/17/2025 | Conditional Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 6/20/2025 | Approved | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/3/2025 | Corrections Issued | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 7/3/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 7/9/2025 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 7/9/2025 | Approved | KEVIN BERBERYAN |
| Rough-Elec/Plmb/HVAC | 7/9/2025 | Approved | KEVIN BERBERYAN |
| Insulation | 7/11/2025 | Corrections Issued | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 7/11/2025 | Approved | MICHAEL CORTEZ |
| Drywall Nailing | 7/16/2025 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 9/3/2025 | Approved | KEVIN BERBERYAN |
| Final | 9/3/2025 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Final | 9/3/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Green Building Rough | 9/3/2025 | Approved | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 9/3/2025 | SGSOV Approved | KEVIN BERBERYAN |
| Smoke Detectors | 9/3/2025 | Approved | KEVIN BERBERYAN |
| Final | 9/22/2025 | OK to Issue CofO | KEVIN BERBERYAN |
| Green Building Final | 9/22/2025 | Approved | KEVIN BERBERYAN |