5650 N LEMP AVE 91601
Certificate Information: 5650 N LEMP AVE 91601
- Application / Permit
- 24014-20000-00538
- Plan Check / Job No.
- B24VN01690
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN CONVERT (E) DETACHED GARAGE TO ADU WITH (N) ADDITION PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 5/15/2024
- Issuing Office
- Current Status
- CofO Issued on 10/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/13/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/16/2024 | JOHNPAUL ISIP |
| Corrections Issued | 2/17/2024 | JOHNPAUL ISIP |
| Plan Check Approved | 3/26/2024 | AMY GUEVARRA |
| Issued | 5/15/2024 | APPLICANT |
| CofO in Progress | 9/30/2025 | JAVIER RAMOS JR |
| CofO Issued | 10/23/2025 | RUBEN SALAS |
| Permit Finaled | 10/23/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 2/24/2024 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 2/24/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/5/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 3/5/2024 | EDGAR ALCARAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/17/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Deputy Drilled-In Anchors | 6/20/2024 | Conditional Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 6/20/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2024 | Approved | CHRISTOPHER ROJAS |
| Gas Test | 9/24/2024 | Approved | CHRISTOPHER ROJAS |
| Gas Test | 9/25/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 10/23/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 10/23/2024 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 10/23/2024 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 10/23/2024 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 10/23/2024 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 10/30/2024 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 10/30/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Insulation | 11/1/2024 | Conditional Approval | LOUIS ESCOTO |
| Insulation | 11/6/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Drywall Nailing | 11/12/2024 | Approved | CHRISTOPHER ROJAS |
| Insulation | 11/12/2024 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 11/12/2024 | Approved | CHRISTOPHER ROJAS |
| Shower Pan | 11/12/2024 | Approved | CHRISTOPHER ROJAS |
| Underground Mechanical | 12/12/2024 | Approved | CHRISTOPHER ROJAS |
| Gas Test | 9/5/2025 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 9/18/2025 | Approved | JAVIER RAMOS JR |
| Final | 9/18/2025 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 9/18/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 9/18/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 9/18/2025 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 9/18/2025 | SGSOV Approved | JAVIER RAMOS JR |
| Service/Power Release | 9/18/2025 | Approved | JAVIER RAMOS JR |
| Smoke Detectors | 9/18/2025 | Approved | JAVIER RAMOS JR |
| Final | 9/23/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Final | 9/30/2025 | OK to Issue CofO | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 9/30/2025 | Approved | JAVIER RAMOS JR |