5650 N LEMP AVE 91601

Certificate Information: 5650 N LEMP AVE 91601

Application / Permit
24014-20000-00538
Plan Check / Job No.
B24VN01690
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN CONVERT (E) DETACHED GARAGE TO ADU WITH (N) ADDITION PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 5/15/2024
Issuing Office
Current Status
CofO Issued on 10/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/13/2024 APPLICANT
Assigned to Plan Check Engineer 2/16/2024 JOHNPAUL ISIP
Corrections Issued 2/17/2024 JOHNPAUL ISIP
Plan Check Approved 3/26/2024 AMY GUEVARRA
Issued 5/15/2024 APPLICANT
CofO in Progress 9/30/2025 JAVIER RAMOS JR
CofO Issued 10/23/2025 RUBEN SALAS
Permit Finaled 10/23/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/24/2024 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 2/24/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 3/5/2024 EDGAR ALCARAZ
Sewer availability Cleared 3/5/2024 EDGAR ALCARAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22814 DOLOROSA ST      WOODLAND HILLS, CA 91367

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 6/17/2024 Partial Approval CHRISTOPHER ROJAS
Deputy Drilled-In Anchors 6/20/2024 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 6/20/2024 Corrections Issued CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 9/24/2024 Approved CHRISTOPHER ROJAS
Gas Test 9/24/2024 Approved CHRISTOPHER ROJAS
Gas Test 9/25/2024 Not Ready for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 10/23/2024 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 10/23/2024 Approved CHRISTOPHER ROJAS
Green Building Rough 10/23/2024 Approved CHRISTOPHER ROJAS
HVAC-Rough 10/23/2024 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 10/23/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 10/30/2024 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 10/30/2024 Partial Approval CHRISTOPHER ROJAS
Insulation 11/1/2024 Conditional Approval LOUIS ESCOTO
Insulation 11/6/2024 Corrections Issued CHRISTOPHER ROJAS
Drywall Nailing 11/12/2024 Approved CHRISTOPHER ROJAS
Insulation 11/12/2024 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 11/12/2024 Approved CHRISTOPHER ROJAS
Shower Pan 11/12/2024 Approved CHRISTOPHER ROJAS
Underground Mechanical 12/12/2024 Approved CHRISTOPHER ROJAS
Gas Test 9/5/2025 Approved JAVIER RAMOS JR
ELECTRICAL-Final 9/18/2025 Approved JAVIER RAMOS JR
Final 9/18/2025 Corrections Issued JAVIER RAMOS JR
Green Building Final 9/18/2025 Approved JAVIER RAMOS JR
HVAC-Final 9/18/2025 Approved JAVIER RAMOS JR
PLUMBING-Final 9/18/2025 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 9/18/2025 SGSOV Approved JAVIER RAMOS JR
Service/Power Release 9/18/2025 Approved JAVIER RAMOS JR
Smoke Detectors 9/18/2025 Approved JAVIER RAMOS JR
Final 9/23/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Final 9/30/2025 OK to Issue CofO JAVIER RAMOS JR
Footing/Foundation/Slab 9/30/2025 Approved JAVIER RAMOS JR