19217 W OLYMPIA ST 91326

Certificate Information: 19217 W OLYMPIA ST 91326

Application / Permit
24014-20000-00535
Plan Check / Job No.
B24VN01668
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. PROPOSED 2-STORY ACCESSORY DWELLING UNIT PER ORDINANCE.
Permit Issued
Issued on 9/25/2024
Issuing Office
Current Status
CofO Issued on 4/4/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/12/2024 APPLICANT
Assigned to Plan Check Engineer 2/22/2024 MICHAEL LOPEZ
Corrections Issued 3/7/2024 MICHAEL LOPEZ
Quality Review Completed 3/7/2024 GARO TELMI
Applicant returned to address corrections 6/4/2024 MICHAEL LOPEZ
Applicant returned to address corrections 6/24/2024 MICHAEL LOPEZ
Applicant returned to address corrections 7/19/2024 MICHAEL LOPEZ
Plan Check Approved 9/18/2024 MICHAEL LOPEZ
Issued 9/25/2024 APPLICANT
CofO in Progress 12/15/2025 DAVID SCANTLIN
Permit Finaled 4/4/2026 MICHAEL PELHAM
CofO Issued 4/4/2026 MICHAEL PELHAM
Permit Finaled 4/4/2026 MICHAEL PELHAM

Permit Application Clearance Information

Address approval Cleared 3/19/2024 BIAINA HARITUNIAN
Miscellaneous Cleared 3/19/2024 BRENNEN OBETO
Roof/Waste drainage to street Cleared 3/19/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 3/20/2024 BIAINA HARITUNIAN
Sewer availability Cleared 3/20/2024 BIAINA HARITUNIAN
Grading Pre-Inspection Cleared 3/21/2024 CHARLES POWELL
GPI Written Notices Cleared 6/24/2024 GERMAN RODRIGUEZ MENDOZA

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/28/2025 Corrections Issued DAVID SCANTLIN
Pre-Inspection 1/28/2025 Not Ready for Inspection DAVID SCANTLIN
Excavation/Setback/Form/Re-Bar 2/4/2025 Approved DAVID SCANTLIN
Pre-Inspection 2/4/2025 Approved DAVID SCANTLIN
PLUMBING-Rough 3/5/2025 Partial Approval DAVID SCANTLIN
Wood Frame 3/5/2025 Partial Approval DAVID SCANTLIN
Insulation 3/18/2025 Partial Approval KRISTEN CAUSEY
Drywall Nailing 3/24/2025 Not Ready for Inspection DAVID SCANTLIN
Wood Frame 3/24/2025 Not Ready for Inspection DAVID SCANTLIN
Wood Frame 4/8/2025 Partial Approval DAVID SCANTLIN
ELECTRICAL-Rough 5/7/2025 Approved DAVID SCANTLIN
HVAC-Rough 5/7/2025 Approved DAVID SCANTLIN
PLUMBING-Rough 5/7/2025 Approved DAVID SCANTLIN
Wood Frame 5/7/2025 Partial Approval DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 5/14/2025 Partial Approval KRISTEN CAUSEY
BUILDING-Rough-Frame 5/27/2025 Approved DAVID SCANTLIN
Green Building Rough 5/27/2025 Approved DAVID SCANTLIN
Insulation 5/27/2025 Not Ready for Inspection DAVID SCANTLIN
Interior/Exterior Lathing 5/27/2025 Partial Approval DAVID SCANTLIN
Verify Sprinkler Sign Off 5/27/2025 Approved DAVID SCANTLIN
Drywall Nailing 6/6/2025 Approved KRISTEN CAUSEY
Shower Pan 6/16/2025 Approved SCOTT SOBEL
Interior/Exterior Lathing 6/20/2025 Partial Approval ARUTYUN MADATYAN
BUILDING-Rough-Frame 9/24/2025 Corrections Issued DAVID SCANTLIN
ELECTRICAL-Rough 9/24/2025 Partial Approval DAVID SCANTLIN
ELECTRICAL-Rough 10/8/2025 Not Ready for Inspection DAVID SCANTLIN
ELECTRICAL-Final 10/23/2025 Partial Inspection KRISTEN CAUSEY
Special/Order Compliance 11/4/2025 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 11/24/2025 Approved DAVID SCANTLIN
Final 11/24/2025 Corrections Issued DAVID SCANTLIN
Footing/Foundation/Slab 11/24/2025 Approved DAVID SCANTLIN
Green Building Final 11/24/2025 Not Ready for Inspection DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 11/24/2025 SGSOV Approved DAVID SCANTLIN
Service/Power Release 11/24/2025 Not Ready for Inspection DAVID SCANTLIN
Smoke Detectors 11/24/2025 Approved DAVID SCANTLIN
Final 12/12/2025 OK to Issue CofO DAVID SCANTLIN
Green Building Final 12/12/2025 Approved DAVID SCANTLIN
Service/Power Release 12/12/2025 Approved DAVID SCANTLIN
Special/Order Compliance 2/6/2026 Corrections Issued DAVID SCANTLIN
Special/Order Compliance 4/1/2026 Approved DAVID SCANTLIN