12918 W CROWLEY ST 91331
Certificate Information: 12918 W CROWLEY ST 91331
- Application / Permit
- 24014-20000-00531
- Plan Check / Job No.
- B24VN01644
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan - ground floor addition to (e) 1-story SFD w/ attached ADU R3 occupancy NFPA 13D sprinklered throughout
- Permit Issued
- Issued on 5/7/2024
- Issuing Office
- Current Status
- Issued on 5/7/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/8/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2024 | KELVIN CHUONG |
| Corrections Issued | 2/13/2024 | KELVIN CHUONG |
| Plan Check Approved | 4/30/2024 | JOSEPH RAFOLS |
| Issued | 5/7/2024 | APPLICANT |
Permit Application Clearance Information
| Sewer availability | Cleared | 2/21/2024 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/22/2024 | CARLOS RAMIREZ |
| Hydrant and Access approval | Cleared | 3/14/2024 | MATTHEW CRAIG |
| Low Impact Development (LID) | Cleared | 4/25/2024 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 4/25/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/2/2025 | Conditional Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 4/9/2025 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Rough | 4/9/2025 | Partial Approval | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 12/30/2025 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/30/2025 | Partial Approval | VINCENT HANLEY |
| Footing/Foundation/Slab | 12/30/2025 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2026 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 3/17/2026 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 3/17/2026 | Partial Approval | OGANES TARAKHCHYAN |
| HVAC-Rough | 5/13/2026 | Approved | OGANES TARAKHCHYAN |
| Wood Frame | 5/13/2026 | Approved | OGANES TARAKHCHYAN |