6843-6845 N DE CELIS PL 91406
Certificate Information: 6843-6845 N DE CELIS PL 91406
- Application / Permit
- 24014-20000-00488
- Plan Check / Job No.
- B24VN01479
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: CONVERT (E) ATTACHED CARPORT INTO A (N) ACCESSORY DWELLING UNIT TO COMPLY WITH GCS 65852.2(e)(1)(A) AND INTO A (N) BREEZEWAY PER ENGINEERING
- Permit Issued
- Issued on 3/22/2024
- Issuing Office
- Current Status
- CofO Issued on 11/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/7/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/9/2024 | ALFRED RAMIREZ |
| Corrections Issued | 2/10/2024 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 3/11/2024 | ALFRED RAMIREZ |
| Plan Check Approved | 3/20/2024 | ALFRED RAMIREZ |
| Issued | 3/22/2024 | APPLICANT |
| CofO in Progress | 11/18/2024 | GAREN HAYRAPETYAN |
| CofO in Progress | 11/19/2024 | RAUL OLAGI |
| CofO in Progress | 11/19/2024 | GAREN HAYRAPETYAN |
| Permit Finaled | 11/22/2024 | RUBEN SALAS |
| CofO Issued | 11/22/2024 | RUBEN SALAS |
| Permit Finaled | 11/22/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 2/24/2024 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 2/24/2024 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 2/26/2024 | MARKOS PEREZ-BRAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Castillo,, Margarito; Lic. No.: NA4808 | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/6/2024 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 5/13/2024 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 5/13/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 5/15/2024 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 5/15/2024 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 5/20/2024 | Corrections Issued | RAUL OLAGI |
| Sewer | 5/20/2024 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 5/23/2024 | Approved | RAUL OLAGI |
| Sewer | 5/23/2024 | Approved | RAUL OLAGI |
| Footing/Foundation/Slab | 5/24/2024 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 6/28/2024 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 6/28/2024 | Corrections Issued | RAUL OLAGI |
| HVAC-Rough | 6/28/2024 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 6/28/2024 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 7/10/2024 | Approved | RAUL OLAGI |
| ELECTRICAL-Rough | 7/10/2024 | Approved | RAUL OLAGI |
| HVAC-Rough | 7/10/2024 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 7/10/2024 | Partial Approval | RAUL OLAGI |
| PLUMBING-Rough | 7/10/2024 | Approved | RAUL OLAGI |
| Insulation | 7/15/2024 | Approved | SALVADOR MARTINEZ |
| Drywall Nailing | 7/19/2024 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 7/19/2024 | Approved | RAUL OLAGI |
| Shower Pan | 7/19/2024 | Approved | RAUL OLAGI |
| Final | 11/4/2024 | Corrections Issued | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 11/4/2024 | SGSOV Approved | GAREN HAYRAPETYAN |
| Smoke Detectors | 11/4/2024 | Approved | GAREN HAYRAPETYAN |
| Final | 11/18/2024 | OK to Issue CofO | GAREN HAYRAPETYAN |