6843-6845 N DE CELIS PL 91406

Certificate Information: 6843-6845 N DE CELIS PL 91406

Application / Permit
24014-20000-00488
Plan Check / Job No.
B24VN01479
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: CONVERT (E) ATTACHED CARPORT INTO A (N) ACCESSORY DWELLING UNIT TO COMPLY WITH GCS 65852.2(e)(1)(A) AND INTO A (N) BREEZEWAY PER ENGINEERING
Permit Issued
Issued on 3/22/2024
Issuing Office
Current Status
CofO Issued on 11/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/7/2024 APPLICANT
Assigned to Plan Check Engineer 2/9/2024 ALFRED RAMIREZ
Corrections Issued 2/10/2024 ALFRED RAMIREZ
Applicant returned to address corrections 3/11/2024 ALFRED RAMIREZ
Plan Check Approved 3/20/2024 ALFRED RAMIREZ
Issued 3/22/2024 APPLICANT
CofO in Progress 11/18/2024 GAREN HAYRAPETYAN
CofO in Progress 11/19/2024 RAUL OLAGI
CofO in Progress 11/19/2024 GAREN HAYRAPETYAN
Permit Finaled 11/22/2024 RUBEN SALAS
CofO Issued 11/22/2024 RUBEN SALAS
Permit Finaled 11/22/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/24/2024 MARKOS PEREZ-BRAN
Sewer availability Cleared 2/24/2024 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 2/26/2024 MARKOS PEREZ-BRAN

Contact Information

Contractor Owner-Builder       ,
Engineer Castillo,, Margarito; Lic. No.: NA4808       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/6/2024 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 5/13/2024 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 5/13/2024 Corrections Issued SALVADOR MARTINEZ
Footing/Foundation/Slab 5/15/2024 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 5/15/2024 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 5/20/2024 Corrections Issued RAUL OLAGI
Sewer 5/20/2024 Corrections Issued RAUL OLAGI
PLUMBING-Rough 5/23/2024 Approved RAUL OLAGI
Sewer 5/23/2024 Approved RAUL OLAGI
Footing/Foundation/Slab 5/24/2024 Approved RAUL OLAGI
BUILDING-Rough-Frame 6/28/2024 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 6/28/2024 Corrections Issued RAUL OLAGI
HVAC-Rough 6/28/2024 Corrections Issued RAUL OLAGI
PLUMBING-Rough 6/28/2024 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 7/10/2024 Approved RAUL OLAGI
ELECTRICAL-Rough 7/10/2024 Approved RAUL OLAGI
HVAC-Rough 7/10/2024 Approved RAUL OLAGI
Interior/Exterior Lathing 7/10/2024 Partial Approval RAUL OLAGI
PLUMBING-Rough 7/10/2024 Approved RAUL OLAGI
Insulation 7/15/2024 Approved SALVADOR MARTINEZ
Drywall Nailing 7/19/2024 Approved RAUL OLAGI
Interior/Exterior Lathing 7/19/2024 Approved RAUL OLAGI
Shower Pan 7/19/2024 Approved RAUL OLAGI
Final 11/4/2024 Corrections Issued GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 11/4/2024 SGSOV Approved GAREN HAYRAPETYAN
Smoke Detectors 11/4/2024 Approved GAREN HAYRAPETYAN
Final 11/18/2024 OK to Issue CofO GAREN HAYRAPETYAN