17370 W CHASE ST 91325

Certificate Information: 17370 W CHASE ST 91325

Application / Permit
24014-20000-00484
Plan Check / Job No.
B24VN01471
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN Irregular shaped addition of two stories 28' 9" x 42' 11 1/2" to the Single family Dwelling, removing the existing rear patio cover and replacing it with a covered deck. All work done per engineer.
Permit Issued
Issued on 10/18/2024
Issuing Office
Current Status
CofO Issued on 4/7/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/5/2024 APPLICANT
Assigned to Plan Check Engineer 2/22/2024 NAREG ATARIAN
Corrections Issued 2/27/2024 NAREG ATARIAN
Quality Review Completed 3/5/2024 OMID HEDAYAT
Applicant returned to address corrections 10/4/2024 NAREG ATARIAN
Applicant returned to address corrections 10/9/2024 NAREG ATARIAN
Plan Check Approved 10/17/2024 NAREG ATARIAN
Issued 10/18/2024 APPLICANT
CofO in Progress 3/9/2026 CHRISTOPHER ROJAS
Permit Finaled 4/7/2026 RUBEN SALAS
CofO Issued 4/7/2026 RUBEN SALAS
Permit Finaled 4/7/2026 RUBEN SALAS

Permit Application Clearance Information

Low Impact Development (LID) Cleared 8/26/2024 LUIS LUVANO
Eng Process Fee Ord 176,300 Cleared 9/5/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 9/5/2024 BIAINA HARITUNIAN
Sewer availability Cleared 9/5/2024 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241
Engineer Espino,, Manuel A; Lic. No.: NA55526       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/18/2024 Partial Approval JAVIER RAMOS JR
Footing/Foundation/Slab 1/15/2025 Corrections Issued JAVIER RAMOS JR
Pre-Inspection 1/15/2025 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 2/26/2025 Partial Approval JAVIER RAMOS JR
Footing/Foundation/Slab 2/26/2025 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 4/25/2025 Corrections Issued CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 4/25/2025 Corrections Issued CHRISTOPHER ROJAS
Deputy Wood Construction 6/27/2025 Conditional Approval RAUL OLAGI
BUILDING-Rough-Frame 7/1/2025 Corrections Issued NICHOLAS TROWBRIDGE
Green Building Rough 7/1/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
ELECTRICAL-Rough 7/14/2025 Corrections Issued NICHOLAS TROWBRIDGE
HVAC-Rough 7/14/2025 Approved NICHOLAS TROWBRIDGE
PLUMBING-Rough 7/14/2025 Corrections Issued NICHOLAS TROWBRIDGE
ELECTRICAL-Rough 7/25/2025 Approved NICHOLAS TROWBRIDGE
HVAC-Rough 7/25/2025 Approved NICHOLAS TROWBRIDGE
PLUMBING-Rough 7/25/2025 Approved NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 8/4/2025 Approved NICHOLAS TROWBRIDGE
Green Building Rough 8/4/2025 Approved NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 8/4/2025 Partial Approval NICHOLAS TROWBRIDGE
Insulation 8/25/2025 Approved NICHOLAS TROWBRIDGE
Drywall Nailing 9/3/2025 Approved NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 9/3/2025 Approved NICHOLAS TROWBRIDGE
Final 11/21/2025 Corrections Issued KEVIN BERBERYAN
Green Building Final 11/21/2025 Not Ready for Inspection KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 11/21/2025 SGSOV Approved KEVIN BERBERYAN
Smoke Detectors 11/21/2025 Approved KEVIN BERBERYAN
Final 3/6/2026 OK to Issue CofO CHRISTOPHER ROJAS
Green Building Final 3/6/2026 Approved CHRISTOPHER ROJAS