17370 W CHASE ST 91325
Certificate Information: 17370 W CHASE ST 91325
- Application / Permit
- 24014-20000-00484
- Plan Check / Job No.
- B24VN01471
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN Irregular shaped addition of two stories 28' 9" x 42' 11 1/2" to the Single family Dwelling, removing the existing rear patio cover and replacing it with a covered deck. All work done per engineer.
- Permit Issued
- Issued on 10/18/2024
- Issuing Office
- Current Status
- CofO Issued on 4/7/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/5/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/22/2024 | NAREG ATARIAN |
| Corrections Issued | 2/27/2024 | NAREG ATARIAN |
| Quality Review Completed | 3/5/2024 | OMID HEDAYAT |
| Applicant returned to address corrections | 10/4/2024 | NAREG ATARIAN |
| Applicant returned to address corrections | 10/9/2024 | NAREG ATARIAN |
| Plan Check Approved | 10/17/2024 | NAREG ATARIAN |
| Issued | 10/18/2024 | APPLICANT |
| CofO in Progress | 3/9/2026 | CHRISTOPHER ROJAS |
| Permit Finaled | 4/7/2026 | RUBEN SALAS |
| CofO Issued | 4/7/2026 | RUBEN SALAS |
| Permit Finaled | 4/7/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 8/26/2024 | LUIS LUVANO |
| Eng Process Fee Ord 176,300 | Cleared | 9/5/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 9/5/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 9/5/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
| Engineer | Espino,, Manuel A; Lic. No.: NA55526 | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/18/2024 | Partial Approval | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 1/15/2025 | Corrections Issued | JAVIER RAMOS JR |
| Pre-Inspection | 1/15/2025 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 2/26/2025 | Partial Approval | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 2/26/2025 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 4/25/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 4/25/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Deputy Wood Construction | 6/27/2025 | Conditional Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 7/1/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Green Building Rough | 7/1/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Rough | 7/14/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| HVAC-Rough | 7/14/2025 | Approved | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 7/14/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Rough | 7/25/2025 | Approved | NICHOLAS TROWBRIDGE |
| HVAC-Rough | 7/25/2025 | Approved | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 7/25/2025 | Approved | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 8/4/2025 | Approved | NICHOLAS TROWBRIDGE |
| Green Building Rough | 8/4/2025 | Approved | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 8/4/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Insulation | 8/25/2025 | Approved | NICHOLAS TROWBRIDGE |
| Drywall Nailing | 9/3/2025 | Approved | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 9/3/2025 | Approved | NICHOLAS TROWBRIDGE |
| Final | 11/21/2025 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Final | 11/21/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 11/21/2025 | SGSOV Approved | KEVIN BERBERYAN |
| Smoke Detectors | 11/21/2025 | Approved | KEVIN BERBERYAN |
| Final | 3/6/2026 | OK to Issue CofO | CHRISTOPHER ROJAS |
| Green Building Final | 3/6/2026 | Approved | CHRISTOPHER ROJAS |