20435 W HAYNES ST 91306
Certificate Information: 20435 W HAYNES ST 91306
- Application / Permit
- 24014-20000-00475
- Plan Check / Job No.
- B24VN01452
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN CONVERT (E) DETACHED GARAGE WITH (N) ADDITION TO ADU PER CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 6/13/2024
- Issuing Office
- Current Status
- CofO Issued on 7/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/5/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/9/2024 | JOHNPAUL ISIP |
| Corrections Issued | 2/14/2024 | JOHNPAUL ISIP |
| Applicant returned to address corrections | 5/2/2024 | JOHNPAUL ISIP |
| Plan Check Approved | 5/18/2024 | JOHNPAUL ISIP |
| Issued | 6/13/2024 | APPLICANT |
| CofO in Progress | 5/28/2025 | ALEXANDER HANDY |
| Permit Finaled | 7/27/2025 | RUBEN SALAS |
| CofO Issued | 7/27/2025 | RUBEN SALAS |
| Permit Finaled | 7/27/2025 | RUBEN SALAS |
Permit Application Clearance Information
| ZI | Cleared | 3/14/2024 | ASHLEY RODARTE |
| Address approval | Cleared | 4/18/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 4/18/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 4/26/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 4/26/2024 | CARLOS AGUILERA |
| Hold | Cleared | 6/24/2024 | KRISTINE BUENAOBRA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 6/17/2024 | Corrections Issued | ALEXANDER HANDY |
| PLUMBING-Rough | 6/17/2024 | Partial Approval | ALEXANDER HANDY |
| Sewer | 6/17/2024 | Approved | ALEXANDER HANDY |
| Footing/Foundation/Slab | 7/3/2024 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 7/25/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| Green Building Rough | 7/25/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| Wood Frame | 7/25/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| ELECTRICAL-Rough | 9/3/2024 | Corrections Issued | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2024 | Corrections Issued | ALEXANDER HANDY |
| PLUMBING-Rough | 9/3/2024 | Corrections Issued | ALEXANDER HANDY |
| ELECTRICAL-Rough | 9/12/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 9/12/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| PLUMBING-Rough | 9/12/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| Interior/Exterior Lathing | 11/5/2024 | Approved | ALEXANDER HANDY |
| Shower Pan | 11/5/2024 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Rough | 11/19/2024 | No Access for Inspection | ALEXANDER HANDY |
| HVAC-Rough | 11/19/2024 | No Access for Inspection | ALEXANDER HANDY |
| HVAC-Rough | 11/22/2024 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 11/22/2024 | Approved | ALEXANDER HANDY |
| Insulation | 11/26/2024 | Conditional Approval | ALEXANDER HANDY |
| Insulation | 12/6/2024 | Conditional Approval | ALEXANDER HANDY |
| Drywall Nailing | 12/17/2024 | Approved | ALEXANDER HANDY |
| Green Building Rough | 12/17/2024 | Approved | ALEXANDER HANDY |
| Service/Power Release | 1/31/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| Service/Power Release | 2/13/2025 | Corrections Issued | JOHN COLEMAN |
| Service/Power Release | 3/6/2025 | Corrections Issued | SCOTT SOBEL |
| Drywall Nailing | 3/19/2025 | Approved | JUAN ALVARADO |
| Service/Power Release | 3/19/2025 | Not Ready for Inspection | JUAN ALVARADO |
| BUILDING-Rough-Frame | 4/22/2025 | Approved | ALEXANDER HANDY |
| Final | 4/22/2025 | Corrections Issued | ALEXANDER HANDY |
| Green Building Final | 4/22/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 4/22/2025 | SGSOV Not Ready | ALEXANDER HANDY |
| Smoke Detectors | 4/22/2025 | Approved | ALEXANDER HANDY |
| Final | 5/13/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| Green Building Final | 5/13/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 5/13/2025 | SGSOV Not Ready | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 5/15/2025 | SGSOV Not Ready | ALEXANDER HANDY |
| ELECTRICAL-Final | 5/27/2025 | Approved | ALEXANDER HANDY |
| Final | 5/27/2025 | OK to Issue CofO | ALEXANDER HANDY |
| Green Building Final | 5/27/2025 | Approved | ALEXANDER HANDY |
| HVAC-Final | 5/27/2025 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 5/27/2025 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 5/27/2025 | SGSOV Approved | ALEXANDER HANDY |
| Service/Power Release | 5/27/2025 | Approved | ALEXANDER HANDY |