11956 W COLLINS ST 91607
Certificate Information: 11956 W COLLINS ST 91607
- Application / Permit
- 24014-20000-00466
- Plan Check / Job No.
- B24VN01417
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: ADDITION AND REMODEL TO (E) S.F.D.
- Permit Issued
- Issued on 4/26/2024
- Issuing Office
- Current Status
- CofO Issued on 9/5/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/2/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/7/2024 | AMY GUEVARRA |
| Corrections Issued | 2/11/2024 | AMY GUEVARRA |
| Applicant returned to address corrections | 2/22/2024 | CAROLEAN BASMA |
| Applicant returned to address corrections | 4/9/2024 | CAROLEAN BASMA |
| Plan Check Approved | 4/25/2024 | CAROLEAN BASMA |
| Issued | 4/26/2024 | APPLICANT |
| TCO Issued (Expire Date: 11-18-2025) | 5/22/2025 | DANIEL ORRANTE |
| CofO in Progress | 8/7/2025 | MISAEL ESPARZA |
| Permit Finaled | 9/5/2025 | RUBEN SALAS |
| CofO Issued | 9/5/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/13/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 2/14/2024 | EDGAR ALCARAZ |
| Low Impact Development (LID) | Cleared | 3/21/2024 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 4/16/2024 | EDGAR ALCARAZ |
Contact Information
| Contractor | Susan Development And Construction Inc; Lic. No.: 1089492-B | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/15/2024 | Conditional Approval | JUAN VALENZUELA |
| Deputy Reinf. Concrete | 5/15/2024 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 5/16/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 5/17/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 5/17/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Deputy Drilled-In Anchors | 5/21/2024 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 5/23/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/6/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 6/6/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Sewer | 6/6/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Underground Mechanical | 6/6/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Deputy Steel/Welding | 7/15/2024 | Partial Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2024 | Corrections Issued | JOSE AVILA |
| Interior/Exterior Lathing | 8/12/2024 | Partial Approval | JOSE AVILA |
| PLUMBING-Rough | 8/12/2024 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 8/14/2024 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 8/14/2024 | Corrections Issued | JOSE AVILA |
| Shower Pan | 8/14/2024 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 9/3/2024 | Approved | JOSE AVILA |
| ELECTRICAL-Rough | 9/3/2024 | Approved | JOSE AVILA |
| Green Building Rough | 9/3/2024 | Approved | JOSE AVILA |
| HVAC-Rough | 9/3/2024 | Approved | JOSE AVILA |
| MERV13>=Rough | 9/3/2024 | Approved | JOSE AVILA |
| PLUMBING-Rough | 9/3/2024 | Approved | JOSE AVILA |
| Insulation | 9/9/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 9/9/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Shower Pan | 9/9/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 9/16/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 4/9/2025 | Corrections Issued | JOSE AVILA |
| PLUMBING-Final | 4/9/2025 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Final | 4/23/2025 | Approved | JOSE AVILA |
| Final | 4/23/2025 | Corrections Issued | JOSE AVILA |
| Green Building Final | 4/23/2025 | Approved | JOSE AVILA |
| HVAC-Final | 4/23/2025 | Approved | JOSE AVILA |
| MERV13>=Final | 4/23/2025 | Approved | JOSE AVILA |
| PLUMBING-Final | 4/23/2025 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 4/23/2025 | SGSOV Approved | JOSE AVILA |
| Service/Power Release | 4/23/2025 | Approved | JOSE AVILA |
| Smoke Detectors | 4/23/2025 | Approved | JOSE AVILA |
| Final | 8/6/2025 | OK to Issue CofO | MISAEL ESPARZA |