857 E 82ND ST 90001
Certificate Information: 857 E 82ND ST 90001
- Application / Permit
- 24014-20000-00452
- Plan Check / Job No.
- B24VN01358
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERT (E) DETACHED GARAGE TO WITH 29'-5" x 23'-5" IRREG.SHAPED ADDITION TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c)-(d). WORK DONE PER ENGINEER DESIGN.
- Permit Issued
- Issued on 2/22/2024
- Issuing Office
- Current Status
- Issued on 2/22/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/1/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/5/2024 | GIOVANNY CHAVEZ |
| Corrections Issued | 2/6/2024 | GIOVANNY CHAVEZ |
| Applicant returned to address corrections | 2/13/2024 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 2/15/2024 | MIROOSH KHACHATOORIAN |
| Issued | 2/22/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 2/7/2024 | ARNULFO CHAMU |
| Roof/Waste drainage to street | Cleared | 2/7/2024 | ARNULFO CHAMU |
| Eng Process Fee Ord 176,300 | Cleared | 2/8/2024 | ARNULFO CHAMU |
| Sewer availability | Cleared | 2/8/2024 | ARNULFO CHAMU |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hernandez,, Jose Antonio; Lic. No.: NA69472 | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/8/2024 | No Access for Inspection | MICHAEL LEWIS |
| Pre-Inspection | 8/20/2024 | Corrections Issued | MICHAEL LEWIS |
| Pre-Inspection | 5/1/2025 | No Access for Inspection | JOHN QUINTANILLA |
| Footing/Foundation/Slab | 5/5/2025 | Partial Inspection | JOHN QUINTANILLA |
| Pre-Inspection | 5/5/2025 | Partial Inspection | JOHN QUINTANILLA |
| PLUMBING-Rough | 6/2/2025 | Partial Approval | ANTHONY RAMOS |
| Sewer | 6/2/2025 | Approved | ANTHONY RAMOS |
| Excavation/Setback/Form/Re-Bar | 6/5/2025 | Corrections Issued | WAYNE REGESTER |
| Footing/Foundation/Slab | 6/5/2025 | Corrections Issued | WAYNE REGESTER |
| Pre-Inspection | 6/10/2025 | Approved | MICHAEL LEWIS |
| Excavation/Setback/Form/Re-Bar | 6/12/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Footing/Foundation/Slab | 6/12/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Excavation/Setback/Form/Re-Bar | 6/16/2025 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 6/16/2025 | Conditional Approval | MICHAEL LEWIS |
| Excavation/Setback/Form/Re-Bar | 6/17/2025 | Approved | JOHN QUINTANILLA |
| Footing/Foundation/Slab | 6/17/2025 | Partial Approval | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 7/7/2025 | Corrections Issued | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 7/7/2025 | Conditional Approval | LUIS CASTRO |
| BUILDING-Rough-Frame | 7/18/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Green Building Rough | 7/18/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 9/17/2025 | Corrections Issued | JOHN QUINTANILLA |
| Green Building Rough | 9/17/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| PLUMBING-Rough | 9/17/2025 | Corrections Issued | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2025 | Approved | BRENDAN MORELLI |
| PLUMBING-Rough | 9/19/2025 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Rough | 9/23/2025 | Corrections Issued | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 9/26/2025 | Corrections Issued | JOSH MEISTER |
| HVAC-Rough | 10/27/2025 | No Access for Inspection | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 10/28/2025 | Corrections Issued | BARRY HACHE |
| Wood Frame | 10/28/2025 | Corrections Issued | BARRY HACHE |
| ELECTRICAL-Rough | 11/21/2025 | Approved | JOHN QUINTANILLA |
| HVAC-Rough | 11/21/2025 | Approved | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 11/21/2025 | Approved | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 11/25/2025 | Approved | JOHN QUINTANILLA |
| Green Building Rough | 11/25/2025 | Approved | JOHN QUINTANILLA |
| Insulation | 12/12/2025 | Corrections Issued | ANTHONY RAMOS |
| Drywall Nailing | 12/19/2025 | Approved | ANTHONY RAMOS |
| Insulation | 12/19/2025 | Approved | ANTHONY RAMOS |
| Service/Power Release | 4/6/2026 | No Access for Inspection | JOHN QUINTANILLA |
| Pre-Inspection | 5/29/2026 | No Access for Inspection | RAUL BARAJAS |