14014 W LA MAIDA ST 91423
Certificate Information: 14014 W LA MAIDA ST 91423
- Application / Permit
- 24014-20000-00450
- Plan Check / Job No.
- B24VN01353
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION TO AND CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 4/16/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/1/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/8/2024 | JEROME MAGAT PALMA |
| Corrections Issued | 2/9/2024 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 2/23/2024 | APPLICANT |
| Applicant returned to address corrections | 3/26/2024 | ARAMIK SHAHMIRZAIAN |
| Plan Check Approved | 3/29/2024 | GURUNATH NESARAJAH |
| Issued | 4/16/2024 | APPLICANT |
| CofO in Progress | 2/27/2025 | MISAEL ESPARZA |
| Permit Finaled | 3/18/2025 | RUBEN SALAS |
| CofO Issued | 3/18/2025 | RUBEN SALAS |
| Permit Finaled | 3/18/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/9/2024 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 3/9/2024 | EDGAR ALCARAZ |
| ZI | Cleared | 3/12/2024 | STEVEN WECHSLER |
| Eng Process Fee Ord 176,300 | Cleared | 3/21/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 3/21/2024 | EDGAR ALCARAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wu,, Harold Ping-Hung; Lic. No.: C35693 | 1168 SAN GABRIEL BLVD NO N ROSEMEAD, CA 91770 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/20/2024 | Partial Approval | MISAEL ESPARZA |
| Deputy Drilled-In Anchors | 5/22/2024 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 5/29/2024 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Rough | 7/22/2024 | Approved | KEVIN BERBERYAN |
| HVAC-Rough | 7/22/2024 | Corrections Issued | KEVIN BERBERYAN |
| PLUMBING-Rough | 7/22/2024 | Approved | KEVIN BERBERYAN |
| Wood Frame | 7/22/2024 | Corrections Issued | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 8/1/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 8/1/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 8/1/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| MERV13>=Rough | 8/1/2024 | Approved | MISAEL ESPARZA |
| Wood Frame | 8/1/2024 | Partial Approval | MISAEL ESPARZA |
| Gas Test | 8/15/2024 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 8/15/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 8/15/2024 | Approved | MISAEL ESPARZA |
| Sewer | 8/15/2024 | Approved | MISAEL ESPARZA |
| Shower Pan | 8/15/2024 | Approved | MISAEL ESPARZA |
| Underground Mechanical | 8/15/2024 | Partial Inspection | MISAEL ESPARZA |
| Wood Frame | 8/15/2024 | Approved | MISAEL ESPARZA |
| Insulation | 8/20/2024 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 8/20/2024 | Partial Approval | MISAEL ESPARZA |
| Drywall Nailing | 8/27/2024 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 10/2/2024 | Approved | MISAEL ESPARZA |
| Underground Mechanical | 10/2/2024 | Partial Approval | MISAEL ESPARZA |
| ELECTRICAL-Final | 11/26/2024 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Final | 11/26/2024 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Final | 11/26/2024 | Corrections Issued | MISAEL ESPARZA |
| Service/Power Release | 11/26/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Interior/Exterior Lathing | 12/10/2024 | Partial Inspection | MISAEL ESPARZA |
| Shower Pan | 12/10/2024 | Partial Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 2/26/2025 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 2/26/2025 | Approved | MISAEL ESPARZA |
| Final | 2/26/2025 | OK to Issue CofO | MISAEL ESPARZA |
| Green Building Final | 2/26/2025 | Approved | MISAEL ESPARZA |
| Green Building Rough | 2/26/2025 | Approved | MISAEL ESPARZA |
| HVAC-Final | 2/26/2025 | Approved | MISAEL ESPARZA |
| MERV13>=Final | 2/26/2025 | Approved | MISAEL ESPARZA |
| PLUMBING-Final | 2/26/2025 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 2/26/2025 | SGSOV Approved | MISAEL ESPARZA |
| Service/Power Release | 2/26/2025 | Approved | MISAEL ESPARZA |
| Smoke Detectors | 2/26/2025 | Approved | MISAEL ESPARZA |