11915-11917 W STRATHERN ST 91605
Certificate Information: 11915-11917 W STRATHERN ST 91605
- Application / Permit
- 24014-20000-00442
- Plan Check / Job No.
- B24VN01322
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED GARAGE TO A (N) ACCESSORY DWELLING UNIT AND 18'-5" x 31'-0" ADDITION W/ (N) ROOF FRAMING OVER GARAGE.
- Permit Issued
- Issued on 2/15/2024
- Issuing Office
- Current Status
- CofO Issued on 8/23/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/31/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/7/2024 | JESSE ARELLANO |
| Corrections Issued | 2/8/2024 | JESSE ARELLANO |
| Building Plans Picked Up | 2/9/2024 | APPLICANT |
| Issued | 2/15/2024 | APPLICANT |
| CofO in Progress | 8/15/2024 | MATTHEW NELSON |
| CofO in Progress | 8/15/2024 | MATTHEW NELSON |
| CofO in Progress | 8/15/2024 | MATTHEW NELSON |
| CofO Issued | 8/23/2024 | DANIEL ORRANTE |
| Permit Finaled | 8/23/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 2/10/2024 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 2/12/2024 | COLIN LOREDO |
| Sewer availability | Cleared | 2/13/2024 | COLIN LOREDO |
| Low Impact Development (LID) | Cleared | 2/14/2024 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 2/15/2024 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| WILLIAM WREN, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 3/18/2024 | No Access for Inspection | MATTHEW NELSON |
| Pre-Inspection | 4/8/2024 | Corrections Issued | MATTHEW NELSON |
| Pre-Inspection | 4/16/2024 | Corrections Issued | JOHN COLEMAN |
| Deputy Drilled-In Anchors | 4/29/2024 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 4/30/2024 | Corrections Issued | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 5/2/2024 | Partial Approval | MATTHEW NELSON |
| Footing/Foundation/Slab | 5/2/2024 | Partial Approval | MATTHEW NELSON |
| Deputy Drilled-In Anchors | 5/13/2024 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 5/15/2024 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 5/15/2024 | Partial Approval | MATTHEW NELSON |
| BUILDING-Rough-Frame | 5/30/2024 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 5/30/2024 | Approved | MATTHEW NELSON |
| Green Building Rough | 5/30/2024 | Approved | MATTHEW NELSON |
| HVAC-Rough | 5/30/2024 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 5/30/2024 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 6/3/2024 | Approved | MATTHEW NELSON |
| Deputy Wood Construction | 6/5/2024 | Conditional Approval | ROBERT GOLD |
| Insulation | 6/6/2024 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 6/6/2024 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 6/10/2024 | Approved | MATTHEW NELSON |
| Drywall Nailing | 6/11/2024 | Approved | MATTHEW NELSON |
| Shower Pan | 6/20/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 7/9/2024 | Corrections Issued | MATTHEW NELSON |
| Final | 7/9/2024 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 7/9/2024 | Corrections Issued | MATTHEW NELSON |
| HVAC-Final | 7/9/2024 | Corrections Issued | MATTHEW NELSON |
| PLUMBING-Final | 7/9/2024 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 7/9/2024 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 7/9/2024 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 8/14/2024 | Approved | MATTHEW NELSON |
| Smoke Detectors | 8/14/2024 | Approved | MATTHEW NELSON |
| Final | 8/15/2024 | OK to Issue CofO | MATTHEW NELSON |