4433 N LEYDON AVE 91364
Certificate Information: 4433 N LEYDON AVE 91364
- Application / Permit
- 24014-20000-00426
- Plan Check / Job No.
- B24VN01296
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePLan - ground floor addition to (e) 1-story SFD R3/U Occupancy
- Permit Issued
- Issued on 4/15/2024
- Issuing Office
- Current Status
- CofO Issued on 2/24/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/31/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/5/2024 | KHUONG TRUONG |
| Corrections Issued | 2/5/2024 | KHUONG TRUONG |
| Plan Check Approved | 2/14/2024 | KELVIN CHUONG |
| Issued | 4/15/2024 | APPLICANT |
| CofO in Progress | 11/18/2024 | JOHN HAYES |
| Permit Finaled | 2/24/2025 | JOHN JANSON |
| CofO Issued | 2/24/2025 | JOHN JANSON |
| Permit Finaled | 2/24/2025 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/9/2024 | COLIN LOREDO |
| Roof/Waste drainage to street | Cleared | 2/9/2024 | COLIN LOREDO |
| Grading Pre-Inspection | Cleared | 2/10/2024 | CHARLES POWELL |
| Sewer availability | Cleared | 2/10/2024 | COLIN LOREDO |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: NA30383 | , |
| Contractor | Green Works Construction & Design Inc; Lic. No.: 936962-B | , |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/15/2024 | Not Ready for Inspection | JOHN HAYES |
| Underground Mechanical | 5/15/2024 | Corrections Issued | JOHN HAYES |
| Footing/Foundation/Slab | 5/20/2024 | Not Ready for Inspection | JOHN HAYES |
| Underground Mechanical | 5/21/2024 | Partial Approval | JOHN HAYES |
| Underground Mechanical | 5/28/2024 | Corrections Issued | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 5/31/2024 | Partial Approval | JOHN HAYES |
| Underground Mechanical | 5/31/2024 | Partial Approval | JOHN HAYES |
| Deputy Drilled-In Anchors | 6/5/2024 | Approved | JOHN HAYES |
| Footing/Foundation/Slab | 6/5/2024 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 8/7/2024 | Partial Approval | JOHN HAYES |
| ELECTRICAL-Rough | 8/7/2024 | Approved | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2024 | Partial Approval | JOHN HAYES |
| Green Building Rough | 8/7/2024 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 8/7/2024 | Approved | JOHN HAYES |
| PLUMBING-Rough | 8/7/2024 | Approved | JOHN HAYES |
| Wood Frame | 8/7/2024 | Partial Approval | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2024 | Corrections Issued | JOHN HAYES |
| Interior/Exterior Lathing | 8/22/2024 | Partial Approval | JOHN HAYES |
| Shower Pan | 8/22/2024 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 8/27/2024 | Approved | JOHN HAYES |
| Green Building Rough | 8/27/2024 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 8/27/2024 | Partial Approval | JOHN HAYES |
| Insulation | 9/5/2024 | Corrections Issued | JOHN HAYES |
| Insulation | 9/9/2024 | Approved | JOHN HAYES |
| Drywall Nailing | 9/20/2024 | Approved | JOHN HAYES |
| Sewer | 11/7/2024 | Approved | JOHN HAYES |
| ELECTRICAL-Final | 11/15/2024 | Approved | JOHN HAYES |
| Final | 11/15/2024 | OK to Issue CofO | JOHN HAYES |
| Green Building Final | 11/15/2024 | Approved | JOHN HAYES |
| HVAC-Final | 11/15/2024 | Approved | JOHN HAYES |
| PLUMBING-Final | 11/15/2024 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 11/15/2024 | SGSOV Approved | JOHN HAYES |
| Smoke Detectors | 11/15/2024 | Approved | JOHN HAYES |
| Special/Order Compliance | 1/22/2025 | Approved | JOHN HAYES |