6221 N CARPENTER AVE 91606
Certificate Information: 6221 N CARPENTER AVE 91606
- Application / Permit
- 24014-20000-00415
- Plan Check / Job No.
- B24VN01257
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *EPLAN* CONVERT DETACHED STORAGE BUILDING TO NEW TWO STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 4/23/2024
- Issuing Office
- Current Status
- CofO Issued on 11/27/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/31/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/15/2024 | SELLA BENYAMIN |
| Corrections Issued | 2/22/2024 | SELLA BENYAMIN |
| Quality Review Completed | 2/23/2024 | STEVEN KIM |
| Plan Check Approved | 4/19/2024 | SELLA BENYAMIN |
| Issued | 4/23/2024 | APPLICANT |
| CofO in Progress | 10/24/2024 | THOMAS WOODS |
| Permit Finaled | 11/27/2024 | DAVID JAMES |
| CofO Issued | 11/27/2024 | DAVID JAMES |
| Permit Finaled | 11/27/2024 | DAVID JAMES |
Permit Application Clearance Information
| Address approval | Cleared | 3/2/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 3/4/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 3/4/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/29/2024 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 5/2/2024 | Not Ready for Inspection | THOMAS WOODS |
| Pre-Inspection | 5/2/2024 | Corrections Issued | THOMAS WOODS |
| Footing/Foundation/Slab | 6/27/2024 | Not Ready for Inspection | THOMAS WOODS |
| BUILDING-Rough-Frame | 7/3/2024 | No Access for Inspection | THOMAS WOODS |
| Final | 7/3/2024 | No Access for Inspection | THOMAS WOODS |
| Green Building Final | 7/3/2024 | No Access for Inspection | THOMAS WOODS |
| Green Building Rough | 7/3/2024 | No Access for Inspection | THOMAS WOODS |
| SGSOV-Seismic Gas S/O Valve | 7/3/2024 | SGSOV Not Ready | THOMAS WOODS |
| Smoke Detectors | 7/3/2024 | No Access for Inspection | THOMAS WOODS |
| BUILDING-Rough-Frame | 10/23/2024 | Approved | THOMAS WOODS |
| ELECTRICAL-Final | 10/23/2024 | Approved | THOMAS WOODS |
| Final | 10/23/2024 | Not Ready for Inspection | THOMAS WOODS |
| Footing/Foundation/Slab | 10/23/2024 | Approved | THOMAS WOODS |
| Gas Test | 10/23/2024 | Approved | THOMAS WOODS |
| Green Building Final | 10/23/2024 | Approved | THOMAS WOODS |
| Green Building Rough | 10/23/2024 | Approved | THOMAS WOODS |
| HVAC-Final | 10/23/2024 | Approved | THOMAS WOODS |
| PLUMBING-Final | 10/23/2024 | Approved | THOMAS WOODS |
| SGSOV-Seismic Gas S/O Valve | 10/23/2024 | SGSOV Approved | THOMAS WOODS |
| Sewer | 10/23/2024 | Approved | THOMAS WOODS |
| Smoke Detectors | 10/23/2024 | Approved | THOMAS WOODS |
| Final | 10/24/2024 | OK to Issue CofO | THOMAS WOODS |