809 N TOYOPA DR 90272

Certificate Information: 809 N TOYOPA DR 90272

Application / Permit
24014-20000-00406
Plan Check / Job No.
B24VN01228
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL TO EXISTING SINGLE-FAMILY DWELLING AND NEW 6-9" X 19'-6" ADDITION
Permit Issued
Issued on 2/27/2024
Issuing Office
Valley
Current Status
CofO Issued on 12/24/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/30/2024 APPLICANT
Assigned to Plan Check Engineer 2/2/2024 JESSE ARELLANO
Corrections Issued 2/5/2024 JESSE ARELLANO
Building Plans Picked Up 2/8/2024 APPLICANT
Plan Check Approved 2/27/2024 ALEC MOUSAKHANIAN
Issued 2/27/2024 APPLICANT
CofO in Progress 12/19/2024 EVAN COOPER
Permit Finaled 12/24/2024 RICHARD STEINBACH
CofO Issued 12/24/2024 RICHARD STEINBACH
Permit Finaled 12/24/2024 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/23/2024 DINAH GARIN
Roof/Waste drainage to street Cleared 2/23/2024 DINAH GARIN
Sewer availability Cleared 2/23/2024 DINAH GARIN
Grading Pre-Inspection Cleared 2/26/2024 ROBERT PINA

Contact Information

Contractor Owner-Builder       ,
Engineer Saiyadian, Sarnaghi, Tomik; Lic. No.: C89129 1171 JUSTIN AVE APT 3      GLENDALE, CA 91201

Inspector Information

STEPHANIE SWANSON, (213) 469-1255 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/22/2024 Approved EVAN COOPER
BUILDING-Rough-Frame 7/11/2024 Conditional Approval EVAN COOPER
Deputy Wood Construction 7/11/2024 Conditional Approval EVAN COOPER
Green Building Rough 7/11/2024 Not Ready for Inspection EVAN COOPER
PLUMBING-Rough 7/11/2024 Approved EVAN COOPER
Underground Mechanical 7/11/2024 Not Ready for Inspection EVAN COOPER
ELECTRICAL-Rough 7/19/2024 Corrections Issued EVAN COOPER
HVAC-Rough 7/19/2024 Corrections Issued EVAN COOPER
Interior/Exterior Lathing 7/19/2024 Corrections Issued EVAN COOPER
PLUMBING-Rough 7/19/2024 Approved EVAN COOPER
Insulation 7/26/2024 Not Ready for Inspection EVAN COOPER
Interior/Exterior Lathing 7/26/2024 Approved EVAN COOPER
Shower Pan 7/26/2024 Approved EVAN COOPER
Insulation 7/30/2024 Approved EVAN COOPER
Drywall Nailing 8/6/2024 Not Ready for Inspection EVAN COOPER
Drywall Nailing 8/12/2024 Approved EVAN COOPER
BUILDING-Rough-Frame 12/16/2024 Approved EVAN COOPER
ELECTRICAL-Final 12/16/2024 Approved EVAN COOPER
Final 12/16/2024 Conditional Approval EVAN COOPER
Green Building Final 12/16/2024 Approved EVAN COOPER
Green Building Rough 12/16/2024 Approved EVAN COOPER
HVAC-Final 12/16/2024 Approved EVAN COOPER
PLUMBING-Final 12/16/2024 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 12/16/2024 SGSOV Approved EVAN COOPER
Smoke Detectors 12/16/2024 Approved EVAN COOPER
Final 12/19/2024 OK to Issue CofO EVAN COOPER