5300 N TEESDALE AVE 91607

Certificate Information: 5300 N TEESDALE AVE 91607

Application / Permit
24014-20000-00402
Plan Check / Job No.
B24VN01206
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN PROPOSED 39'-9" X 42'-1" IRREGULAR SHAPED 1-STORY ADDITION AND REMODEL TO (E) SFD. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 3/22/2024
Issuing Office
Current Status
CofO Issued on 10/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/29/2024 APPLICANT
Assigned to Plan Check Engineer 2/1/2024 RAPHAEL ROSAS
Corrections Issued 2/5/2024 RAPHAEL ROSAS
Quality Review Completed 2/9/2024 STEVEN KIM
Applicant returned to address corrections 3/12/2024 RAPHAEL ROSAS
Plan Check Approved 3/21/2024 RAPHAEL ROSAS
Issued 3/22/2024 APPLICANT
CofO in Progress 10/18/2024 OGANES TARAKHCHYAN
Permit Finaled 10/22/2024 DANIEL ORRANTE
CofO Issued 10/22/2024 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/14/2024 CARLOS AGUILERA
Sewer availability Cleared 2/14/2024 CARLOS AGUILERA
Miscellaneous Cleared 2/23/2024 FIPE LEILUA
Specific Plan Cleared 2/28/2024 CHRISTIAN PEARSON
ZI Cleared 2/28/2024 CHRISTIAN PEARSON
Low Impact Development (LID) Cleared 2/29/2024 TOMMY YIN
Roof/Waste drainage to street Cleared 3/1/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/26/2024 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 3/27/2024 Approved CHRISTOPHER ROJAS
Footing/Foundation/Slab 3/27/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 4/10/2024 Partial Approval MISAEL ESPARZA
PLUMBING-Rough 4/10/2024 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 4/11/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Gas Test 5/7/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Rough 5/7/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 5/7/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Sewer 5/7/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Underground Mechanical 5/7/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Gas Test 5/10/2024 Partial Approval MISAEL ESPARZA
PLUMBING-Rough 5/10/2024 Approved MISAEL ESPARZA
ELECTRICAL-Rough 5/15/2024 Corrections Issued OGANES TARAKHCHYAN
HVAC-Rough 5/15/2024 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Rough 5/20/2024 Corrections Issued OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 5/20/2024 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Rough 5/30/2024 Corrections Issued OGANES TARAKHCHYAN
HVAC-Rough 5/30/2024 Corrections Issued OGANES TARAKHCHYAN
Shower Pan 5/30/2024 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 6/3/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 6/3/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 6/3/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Rough 6/3/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
HVAC-Rough 6/3/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 6/3/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Wood Frame 6/3/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 6/5/2024 Approved OGANES TARAKHCHYAN
HVAC-Rough 6/5/2024 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 6/5/2024 Partial Approval OGANES TARAKHCHYAN
BUILDING-Rough-Frame 6/7/2024 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 6/7/2024 Approved OGANES TARAKHCHYAN
Green Building Rough 6/7/2024 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 6/7/2024 Corrections Issued OGANES TARAKHCHYAN
Insulation 6/12/2024 Approved SALVADOR MARTINEZ
Interior/Exterior Lathing 6/12/2024 Approved SALVADOR MARTINEZ
Drywall Nailing 6/17/2024 Approved STUART CHAPMAN
Final 10/10/2024 Corrections Issued OGANES TARAKHCHYAN
Green Building Final 10/10/2024 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 10/10/2024 SGSOV Not Ready OGANES TARAKHCHYAN
Smoke Detectors 10/10/2024 Approved OGANES TARAKHCHYAN
Final 10/18/2024 OK to Issue CofO OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 10/18/2024 SGSOV Approved OGANES TARAKHCHYAN
Service/Power Release 10/18/2024 Approved OGANES TARAKHCHYAN