7346 N TOPEKA DR 91335
Certificate Information: 7346 N TOPEKA DR 91335
- Application / Permit
- 24014-20000-00396
- Plan Check / Job No.
- B24VN01197
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(d) & ADD 2-STORIES FOR (4) BEDROOM/(2) FULL BATHROOMS/HALF BATHROOM/LIVING ROOM/DINING ROOM/KITCHN **ePlan**
- Permit Issued
- Issued on 7/8/2024
- Issuing Office
- Current Status
- CofO Issued on 8/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/31/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/15/2024 | NILOOFAR MEHRAIN |
| Corrections Issued | 2/17/2024 | NILOOFAR MEHRAIN |
| Quality Review Completed | 2/21/2024 | JASON HEALEY |
| Applicant returned to address corrections | 2/29/2024 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 3/13/2024 | NILOOFAR MEHRAIN |
| Plan Check Approved | 7/1/2024 | NILOOFAR MEHRAIN |
| Issued | 7/8/2024 | APPLICANT |
| CofO in Progress | 8/9/2025 | ARUTYUN MADATYAN |
| Permit Finaled | 8/21/2025 | JOHN JANSON |
| CofO Issued | 8/21/2025 | JOHN JANSON |
| Permit Finaled | 8/21/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 2/24/2024 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 2/24/2024 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 2/27/2024 | LEE GUILBEAUX |
| Sewer availability | Cleared | 2/27/2024 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 5/8/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 5/8/2024 | RIDWAN HARDY |
| Low Impact Development (LID) | Cleared | 6/25/2024 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 6/26/2024 | LEE GUILBEAUX |
| Hold | Cleared | 9/26/2024 | MARIA VENDIVIL |
Contact Information
| Contractor | Dotz Inc; Lic. No.: 1033830-B | 15500 ERWIN STREET #1011 VAN NUYS, CA 91411 |
| Engineer | Aalam,, Yahya; Lic. No.: C94318 | 3111 4TH ST APT 401 SANTA MONICA, CA 90405 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 10/1/2024 | Partial Approval | JEFFREY BULL |
| Deputy Drilled-In Anchors | 10/18/2024 | Conditional Approval | HENRY KIM |
| Deputy Reinf. Concrete | 10/18/2024 | Conditional Approval | HENRY KIM |
| Footing/Foundation/Slab | 10/21/2024 | Approved | JEFFREY BULL |
| Underground Mechanical | 10/21/2024 | Partial Approval | JEFFREY BULL |
| Deputy Reinf. Concrete | 10/23/2024 | Conditional Approval | JEFFREY BULL |
| Deputy Wood Construction | 11/20/2024 | Conditional Approval | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/25/2024 | Corrections Issued | ARUTYUN MADATYAN |
| Deputy Wood Construction | 12/6/2024 | Conditional Approval | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/31/2024 | Corrections Issued | JOHN COLEMAN |
| ELECTRICAL-Rough | 1/14/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Wood Frame | 1/14/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 2/11/2025 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 2/21/2025 | Approved | ARUTYUN MADATYAN |
| HVAC-Rough | 2/21/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Rough | 2/21/2025 | Approved | ARUTYUN MADATYAN |
| Shower Pan | 2/21/2025 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 3/6/2025 | Partial Approval | ARUTYUN MADATYAN |
| Insulation | 3/18/2025 | Approved | ARUTYUN MADATYAN |
| Drywall Nailing | 3/24/2025 | Approved | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 3/24/2025 | Approved | KRISTEN CAUSEY |
| HVAC-Final | 7/7/2025 | Partial Inspection | KRISTEN CAUSEY |
| ELECTRICAL-Final | 7/10/2025 | Corrections Issued | ROBERT GOLD |
| HVAC-Final | 7/10/2025 | Corrections Issued | ROBERT GOLD |
| PLUMBING-Final | 7/10/2025 | Partial Approval | ROBERT GOLD |
| ELECTRICAL-Final | 7/24/2025 | Approved | ARUTYUN MADATYAN |
| HVAC-Final | 7/24/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Final | 7/24/2025 | Approved | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 7/30/2025 | Approved | JUAN ALVARADO |
| Final | 7/30/2025 | Corrections Issued | JUAN ALVARADO |
| Green Building Final | 7/30/2025 | Approved | JUAN ALVARADO |
| Green Building Rough | 7/30/2025 | Approved | JUAN ALVARADO |
| SGSOV-Seismic Gas S/O Valve | 7/30/2025 | SGSOV Not Ready | JUAN ALVARADO |
| Smoke Detectors | 7/30/2025 | Approved | JUAN ALVARADO |
| Final | 8/4/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 8/4/2025 | SGSOV Approved | ARUTYUN MADATYAN |
| Final | 8/8/2025 | OK to Issue CofO | ARUTYUN MADATYAN |